Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2001 |
Principal Product | Paints and stains |
NAICS | n/a |
SIC | 2851 - Paints And Allied Products |
Sales | $50,000,000-$100,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 6,500,000 Tons |
Production Hrs. Annual | 6,000 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $105,948 | 3,934,800 | kWh | $0.03 |
Electricity Demand | $77,967 | 8,364 | kW-months/year | $9.32 |
Electricity Fees | $6,000 | - | $ | - |
Natural Gas | $156,226 | 17,198 | MMBtu | $9.08 |
TOTAL ENERGY COSTS | $346,141 | |||
RECOMMENDED SAVINGS* | $40,935 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $31,243 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7252 UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM |
Savings: $23,426 Cost: $20,000 |
$(-81) | (-3,000) | $(-113) | (-12) | $23,620 | 2,601 | - | - | - | - |
$(-81) (-3,000) kWh |
$(-113) (-12) kW-months/year |
$23,620 2,601 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,719 Cost: $800 |
- | - | - | - | $1,719 | 189 | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,719 189 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2163 USE MINIMUM STEAM OPERATING PRESSURE |
Savings: $2,014 Cost: $250 |
- | - | - | - | $2,014 | 222 | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,014 222 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $1,453 Cost: $6,000 |
$3,542 | 131,175 | $2,825 | 300 | $(-4,914) | (-541) | - | - | - | - |
$3,542 131,175 kWh |
$2,825 300 kW-months/year |
$(-4,914) (-541) MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,002 Cost: $1,028 |
$590 | 21,864 | $412 | 44 | - | - | - | - | - | - |
$590 21,864 kWh |
$412 44 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $2,631 Cost: - |
- | - | $2,631 | 280 | - | - | - | - | - | - |
- - kWh |
$2,631 280 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,506 Cost: $1,239 |
$751 | 27,814 | $481 | 51 | - | - | - | - | $2,274 | - |
$751 27,814 kWh |
$481 51 kW-months/year |
- - MMBtu |
- - $ |
$2,274 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.212 ADOPT IN-HOUSE MATERIAL GENERATION |
Savings: $5,184 Cost: $9,200 |
$(-470) | (-17,407) | $(-146) | (-15) | - | - | $(-500) | - | $6,300 | - |
$(-470) (-17,407) kWh |
$(-146) (-15) kW-months/year |
- - MMBtu |
$(-500) - $ |
$6,300 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $40,935 Cost: $38,517 |
$4,332 | 160,446 | $6,090 | 648 | $22,439 | 2,471 | $(-500) | - | $8,574 | - | $4,332 160,446 kWh |
$6,090 648 kW-months/year |
$22,439 2,471 MMBtu |
$(-500) - $ |
$8,574 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $31,243 Cost: $27,050 |
$3,461 | 128,175 | $5,343 | 568 | $22,439 | 2,471 | - | - | - | - | $3,461 128,175 kWh |
$5,343 568 kW-months/year |
$22,439 2,471 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Ancillary Material Cost |