IAC Assessment: NC0374
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: NC0374
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center North Carolina State
Assessment Year 2008
Principal Product Replacement automotive windshields
NAICS 327215 - Glass Product Manufacturing Made of Purchased Glass
SIC 3231 - Products Of Purchased Glass
Sales $100,000,000-$500,000,000
# of Employees 450
Plant Area (Sq.Ft.) 350,000
Annual Production 1,400,000 Pieces
Production Hrs. Annual 7,200
Location (State) NC
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $615,982 16,266,400 kWh $0.04
Electricity Demand $577,432 30,012 kW-months/year $19.24
Electricity Fees $361 - $ -
Natural Gas $140,228 12,332 MMBtu $11.37
TOTAL ENERGY COSTS $1,334,003
RECOMMENDED SAVINGS* $107,880 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $96,227
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ $
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$32,923
Cost:
$63,000
$20,590 543,593 $12,333 670 - - - - $20,590
543,593
kWh
$12,333
670
kW-months/year
-
-
$
-
-
$
02: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR Savings:
$5,372
Cost:
$18,000
$5,372 141,833 - - - - - - $5,372
141,833
kWh
-
-
kW-months/year
-
-
$
-
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,977
Cost:
$100
$2,988 78,870 $1,989 108 $(-1,200) - $(-800) - $2,988
78,870
kWh
$1,989
108
kW-months/year
$(-1,200)
-
$
$(-800)
-
$
04: 2.5194 REDESIGN PROCESS Savings:
$11,653
Cost:
$22,000
$6,436 166,920 $5,217 283 - - - - $6,436
166,920
kWh
$5,217
283
kW-months/year
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,040
Cost:
$7,000
$576 15,219 $464 25 - - - - $576
15,219
kWh
$464
25
kW-months/year
-
-
$
-
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$53,915
Cost:
$100,000
$29,104 743,040 $24,811 1,238 - - - - $29,104
743,040
kWh
$24,811
1,238
kW-months/year
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$107,880
Cost:
$210,100
$65,066 1,689,475 $44,814 2,324 $(-1,200) - $(-800) - $65,066
1,689,475
kWh
$44,814
2,324
kW-months/year
$(-1,200)
-
$
$(-800)
-
$
TOTAL IMPLEMENTED Savings:
$96,227
Cost:
$188,100
$58,630 1,522,555 $39,597 2,041 $(-1,200) - $(-800) - $58,630
1,522,555
kWh
$39,597
2,041
kW-months/year
$(-1,200)
-
$
$(-800)
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost