Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2011 |
Principal Product | Cartons for food |
NAICS | 322212 - Folding Paperboard Box Manufacturing |
SIC | 2657 - Folding Paperboard Boxes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 155 |
Plant Area (Sq.Ft.) | 128,000 |
Annual Production | 90,000,000 Pieces |
Production Hrs. Annual | 8,400 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $255,707 | 6,890,100 | kWh | $0.04 |
Electricity Demand | $130,597 | 14,730 | kW-months/year | $8.87 |
Electricity Fees | $6,127 | - | $ | - |
Natural Gas | $24,069 | 2,110 | MMBtu | $11.41 |
TOTAL ENERGY COSTS | $416,500 | |||
RECOMMENDED SAVINGS* | $57,845 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $39,591 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $14,162 Cost: $5,000 |
$10,405 | 280,376 | $3,757 | 401 | - | - | - | - | - | - |
$10,405 280,376 kWh |
$3,757 401 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $2,202 Cost: $3,750 |
$1,618 | 43,587 | $584 | 62 | - | - | - | - | - | - |
$1,618 43,587 kWh |
$584 62 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7231 USE RADIANT HEATER FOR SPOT HEATING |
Savings: $3,993 Cost: $10,500 |
- | - | - | - | $3,993 | 350 | - | - | - | - |
- - kWh |
- - kW-months/year |
$3,993 350 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $347 Cost: $100 |
$872 | 23,499 | $315 | 34 | - | - | $(-600) | - | $(-240) | - |
$872 23,499 kWh |
$315 34 kW-months/year |
- - MMBtu |
$(-600) - $ |
$(-240) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $420 Cost: $25 |
- | - | $420 | 50 | - | - | - | - | - | - |
- - kWh |
$420 50 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,542 Cost: $25 |
$1,868 | 50,343 | $674 | 72 | - | - | - | - | - | - |
$1,868 50,343 kWh |
$674 72 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $491 Cost: $700 |
$491 | 13,238 | - | - | - | - | - | - | - | - |
$491 13,238 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $630 Cost: $980 |
$630 | 16,990 | - | - | - | - | - | - | - | - |
$630 16,990 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,465 Cost: $3,975 |
$2,544 | 68,565 | $921 | 98 | - | - | - | - | - | - |
$2,544 68,565 kWh |
$921 98 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $20,987 Cost: $71,380 |
$18,339 | 494,172 | $6,622 | 706 | - | - | $(-5,406) | - | $1,432 | - |
$18,339 494,172 kWh |
$6,622 706 kW-months/year |
- - MMBtu |
$(-5,406) - $ |
$1,432 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $2,306 Cost: $4,600 |
$648 | 17,451 | $1,658 | 177 | - | - | - | - | - | - |
$648 17,451 kWh |
$1,658 177 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 4.625 DEVELOP STANDARD OPERATING PROCEDURES |
Savings: $6,300 Cost: $3,000 |
- | - | - | - | - | - | $6,300 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$6,300 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $57,845 Cost: $104,035 |
$37,415 | 1,008,221 | $14,951 | 1,600 | $3,993 | 350 | $294 | - | $1,192 | - | $37,415 1,008,221 kWh |
$14,951 1,600 kW-months/year |
$3,993 350 MMBtu |
$294 - $ |
$1,192 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $39,591 Cost: $81,435 |
$32,790 | 883,602 | $11,615 | 1,239 | - | - | $(-6,006) | - | $1,192 | - | $32,790 883,602 kWh |
$11,615 1,239 kW-months/year |
- - MMBtu |
$(-6,006) - $ |
$1,192 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost |