Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2012 |
Principal Product | Railroad ties |
NAICS | 321114 - Wood Preservation |
SIC | 2491 - Wood Preserving |
Sales | $10,000,000-$50,000,000 |
# of Employees | 59 |
Plant Area (Sq.Ft.) | 52,000 |
Annual Production | 3,283,000 Thousand Feet |
Production Hrs. Annual | 8,400 |
Location (State) | VA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $150,546 | 3,826,800 | kWh | $0.04 |
Electricity Demand | $92,342 | 9,063 | kW-months/year | $10.19 |
Wood | $232,273 | 91,583 | MMBtu | $2.54 |
Other Energy | $1 | 39,250 | MMBtu | $0.00 |
TOTAL ENERGY COSTS | $475,162 | |||
RECOMMENDED SAVINGS* | $70,795 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $11,863 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Wood | Water Disposal | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Wood | Water Disposal | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1243 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER |
Savings: $9,357 Cost: $35,000 |
- | - | - | - | $9,281 | 3,654 | $76 | 25,200 | - | - | - | - |
- - kWh |
- - kW-months/year |
$9,281 3,654 MMBtu |
$76 25,200 Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $44,787 Cost: $200,000 |
- | - | - | - | $44,787 | 17,633 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$44,787 17,633 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2127 FLASH CONDENSATE TO PRODUCE LOWER PRESSURE STEAM |
Savings: $4,788 Cost: $20,000 |
- | - | - | - | $4,788 | 1,885 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,788 1,885 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,196 Cost: $4,425 |
$1,606 | 40,827 | $590 | 58 | - | - | - | - | - | - | - | - |
$1,606 40,827 kWh |
$590 58 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $3,045 Cost: $6,067 |
$1,985 | 50,466 | $1,060 | 104 | - | - | - | - | - | - | - | - |
$1,985 50,466 kWh |
$1,060 104 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,418 Cost: $9,330 |
$3,224 | 81,959 | $1,194 | 118 | - | - | - | - | - | - | - | - |
$3,224 81,959 kWh |
$1,194 118 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $977 Cost: $231 |
$713 | 18,129 | $264 | 26 | - | - | - | - | - | - | - | - |
$713 18,129 kWh |
$264 26 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,227 Cost: $300 |
$1,508 | 38,338 | $559 | 55 | - | - | - | - | $(-600) | - | $(-240) | - |
$1,508 38,338 kWh |
$559 55 kW-months/year |
- - MMBtu |
- - Tgal |
$(-600) - $ |
$(-240) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $70,795 Cost: $275,353 |
$9,036 | 229,719 | $3,667 | 361 | $58,856 | 23,172 | $76 | 25,200 | $(-600) | - | $(-240) | - | $9,036 229,719 kWh |
$3,667 361 kW-months/year |
$58,856 23,172 MMBtu |
$76 25,200 Tgal |
$(-600) - $ |
$(-240) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $11,863 Cost: $20,353 |
$9,036 | 229,719 | $3,667 | 361 | - | - | - | - | $(-600) | - | $(-240) | - | $9,036 229,719 kWh |
$3,667 361 kW-months/year |
- - MMBtu |
- - Tgal |
$(-600) - $ |
$(-240) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Wood | Water Disposal | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Wood | Water Disposal | Personnel Changes | Ancillary Material Cost |