Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2013 |
Principal Product | Dyed and finished fabrics |
NAICS | 313310 - Textile and Fabric Finishing Mills |
SIC | 2262 - Finishing Plants, Manmade |
Sales | $50,000,000-$100,000,000 |
# of Employees | 165 |
Plant Area (Sq.Ft.) | 459,000 |
Annual Production | 49,000 Thousand Feet |
Production Hrs. Annual | 7,200 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $469,077 | 11,283,000 | kWh | $0.04 |
Electricity Demand | $268,453 | 26,040 | kW-months/year | $10.31 |
Electricity Fees | $940 | - | $ | - |
Natural Gas | $1,107,871 | 233,267 | MMBtu | $4.75 |
TOTAL ENERGY COSTS | $2,738,408 | |||
RECOMMENDED SAVINGS* | $123,829 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $89,196 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2444 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS |
Savings: $52,036 Cost: $15,000 |
- | - | - | - | $52,036 | 11,079 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$52,036 11,079 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1212 OPERATE BOILERS ON HIGH FIRE SETTING |
Savings: $17,607 Cost: $1,000 |
- | - | - | - | $17,607 | 3,939 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$17,607 3,939 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $11,043 Cost: - |
- | - | - | - | $11,043 | 2,351 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$11,043 2,351 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1243 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER |
Savings: $10,670 Cost: $35,000 |
- | - | - | - | $10,270 | 2,187 | $400 | 79,920 | - | - | - | - |
- - kWh |
- - kW-months/year |
$10,270 2,187 MMBtu |
$400 79,920 Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $3,164 Cost: $1,617 |
- | - | - | - | $3,164 | 674 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$3,164 674 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $1,539 Cost: $1,165 |
- | - | - | - | $1,539 | 328 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,539 328 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $1,306 Cost: $1,750 |
- | - | - | - | $1,306 | 278 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,306 278 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $5,104 Cost: $200 |
$2,793 | - | $2,311 | 256 | - | - | - | - | - | - | - | - |
$2,793 - kWh |
$2,311 256 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $8,448 Cost: $18,119 |
$6,134 | 147,449 | $2,224 | 246 | - | - | - | - | - | - | $90 | - |
$6,134 147,449 kWh |
$2,224 246 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
$90 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,040 Cost: $12,800 |
$2,232 | 53,654 | $808 | 89 | - | - | - | - | - | - | - | - |
$2,232 53,654 kWh |
$808 89 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $3,113 Cost: $3,202 |
$3,113 | 74,833 | - | - | - | - | - | - | - | - | - | - |
$3,113 74,833 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,194 Cost: $451 |
$729 | 17,528 | $217 | 24 | - | - | - | - | - | - | $1,248 | - |
$729 17,528 kWh |
$217 24 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
$1,248 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,510 Cost: $100 |
$2,459 | 59,112 | $891 | 99 | - | - | - | - | $(-600) | - | $(-240) | - |
$2,459 59,112 kWh |
$891 99 kW-months/year |
- - MMBtu |
- - Tgal |
$(-600) - $ |
$(-240) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $2,055 Cost: $4,256 |
$1,509 | 36,266 | $546 | 60 | - | - | - | - | - | - | - | - |
$1,509 36,266 kWh |
$546 60 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $123,829 Cost: $94,660 |
$18,969 | 388,842 | $6,997 | 774 | $96,965 | 20,836 | $400 | 79,920 | $(-600) | - | $1,098 | - | $18,969 388,842 kWh |
$6,997 774 kW-months/year |
$96,965 20,836 MMBtu |
$400 79,920 Tgal |
$(-600) - $ |
$1,098 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $89,196 Cost: $53,476 |
$13,063 | 314,009 | $4,686 | 518 | $70,949 | 15,296 | - | - | $(-600) | - | $1,098 | - | $13,063 314,009 kWh |
$4,686 518 kW-months/year |
$70,949 15,296 MMBtu |
- - Tgal |
$(-600) - $ |
$1,098 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Ancillary Material Cost |