Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2019 |
Principal Product | Electric steering units |
NAICS | 336330 - Motor Vehicle Steering and Suspension Components (except Spring) Manufacturing |
SIC | 3714 - Motor Vehicle Parts And Accessories |
Sales | $100,000,000-$500,000,000 |
# of Employees | 210 |
Plant Area (Sq.Ft.) | 125,000 |
Annual Production | 900,000 Units |
Production Hrs. Annual | 6,000 |
Location (State) | VA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $107,107 | 2,208,400 | kWh | $0.05 |
Electricity Demand | $61,831 | 4,280 | kW-months/year | $14.45 |
Natural Gas | $12,554 | 1,679 | MMBtu | $7.48 |
TOTAL ENERGY COSTS | $181,492 | |||
RECOMMENDED SAVINGS* | $21,479 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $15,575 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $11,564 Cost: $40,273 |
$6,855 | 141,341 | $4,709 | 326 | - | - | - | - | - | - |
$6,855 141,341 kWh |
$4,709 326 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $532 Cost: $871 |
$532 | 10,976 | - | - | - | - | - | - | - | - |
$532 10,976 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $240 Cost: $45 |
$150 | 3,096 | $90 | 6 | - | - | - | - | - | - |
$150 3,096 kWh |
$90 6 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,034 Cost: $135 |
$1,523 | 31,392 | $646 | 45 | - | - | $(-90) | - | $(-45) | - |
$1,523 31,392 kWh |
$646 45 kW-months/year |
- - MMBtu |
$(-90) - $ |
$(-45) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $2,962 Cost: $4,000 |
- | - | - | - | $2,962 | 396 | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,962 396 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $2,170 Cost: $9,000 |
$2,170 | 44,760 | - | - | - | - | - | - | - | - |
$2,170 44,760 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $1,977 Cost: $200 |
- | - | $1,977 | 137 | - | - | - | - | - | - |
- - kWh |
$1,977 137 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $21,479 Cost: $54,524 |
$11,230 | 231,565 | $7,422 | 514 | $2,962 | 396 | $(-90) | - | $(-45) | - | $11,230 231,565 kWh |
$7,422 514 kW-months/year |
$2,962 396 MMBtu |
$(-90) - $ |
$(-45) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $15,575 Cost: $40,608 |
$8,378 | 172,733 | $7,332 | 508 | - | - | $(-90) | - | $(-45) | - | $8,378 172,733 kWh |
$7,332 508 kW-months/year |
- - MMBtu |
$(-90) - $ |
$(-45) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost |