IAC Assessment: ND0046
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: ND0046
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Notre Dame Univ.
Assessment Year 1992
Principal Product BOTTOM UNLOADERS
NAICS n/a
SIC 3523 - Farm Machinery And Equipment
Sales $5,000,000-$10,000,000
# of Employees 45
Plant Area (Sq.Ft.) 0
Annual Production 159 Pieces
Production Hrs. Annual 4,000
Location (State) IN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $17,253 242,966 kWh $0.07
Natural Gas $7,617 1,535 MMBtu $4.96
Other Energy $1,633 18 MMBtu $90.72
TOTAL ENERGY COSTS $26,503
RECOMMENDED SAVINGS* $6,663 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $1,306
#|Description Savings
Cost
Status Electricity Usage Natural Gas Other Energy Administrative Changes Electricity Usage Natural Gas Other Energy Administrative Changes
$ kWh $ MMBtu $ MMBtu $ $
01: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$3,760
Cost:
$14,000
- - $3,760 758 - - - - -
-
kWh
$3,760
758
MMBtu
-
-
MMBtu
-
-
$
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$582
Cost:
$4,765
$582 8,206 - - - - - - $582
8,206
kWh
-
-
MMBtu
-
-
MMBtu
-
-
$
03: 2.1332 CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS Savings:
$1,535
Cost:
$1,200
- - $(-98) (-18) $1,633 18 - - -
-
kWh
$(-98)
(-18)
MMBtu
$1,633
18
MMBtu
-
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$582
Cost:
$300
$582 8,206 - - - - - - $582
8,206
kWh
-
-
MMBtu
-
-
MMBtu
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$38
Cost:
$500
$125 1,758 - - - - $(-87) - $125
1,758
kWh
-
-
MMBtu
-
-
MMBtu
$(-87)
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$104
Cost:
$269
$104 1,465 - - - - - - $104
1,465
kWh
-
-
MMBtu
-
-
MMBtu
-
-
$
07: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$62
Cost:
$200
$62 879 - - - - - - $62
879
kWh
-
-
MMBtu
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$6,663
Cost:
$21,234
$1,455 20,514 $3,662 740 $1,633 18 $(-87) - $1,455
20,514
kWh
$3,662
740
MMBtu
$1,633
18
MMBtu
$(-87)
-
$
TOTAL IMPLEMENTED Savings:
$1,306
Cost:
$5,834
$1,393 19,635 - - - - $(-87) - $1,393
19,635
kWh
-
-
MMBtu
-
-
MMBtu
$(-87)
-
$
Savings
Cost
$ kWh $ MMBtu $ MMBtu $ $
Electricity Usage Natural Gas Other Energy Administrative Changes Electricity Usage Natural Gas Other Energy Administrative Changes