Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Nevada |
---|---|
Assessment Year | 1998 |
Principal Product | Dimension Lumber |
NAICS | n/a |
SIC | 2421 - Sawmills And Planing Mills, General |
Sales | $10,000,000-$50,000,000 |
# of Employees | 105 |
Plant Area (Sq.Ft.) | 252,100 |
Annual Production | 41,000,000 Units |
Production Hrs. Annual | 2,470 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $366,956 | 6,291,911 | kWh | $0.06 |
Electricity Demand | $196,577 | 57,768 | kW-months/year | $3.40 |
Electricity Fees | $(-22,228) | - | $ | - |
Natural Gas | $169,015 | 140,588 | MMBtu | $1.20 |
TOTAL ENERGY COSTS | $716,239 | |||
RECOMMENDED SAVINGS* | $152,497 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $2,942 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Administrative Changes | Primary Product | By-product Production | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Administrative Changes | Primary Product | By-product Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2121 INCREASE AMOUNT OF CONDENSATE RETURNED |
Savings: $6,487 Cost: $6,000 |
- | - | - | - | - | - | $6,487 | 2,199 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$6,487 2,199 MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $248 Cost: $200 |
$272 | 4,689 | - | - | $(-24) | - | - | - | - | - | - | - | - | - |
$272 4,689 kWh |
- - kW-months/year |
$(-24) - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $5,011 Cost: $16,200 |
- | - | - | - | $5,011 | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$5,011 - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,858 Cost: $3,052 |
$1,248 | 21,688 | $720 | 212 | $(-110) | - | - | - | - | - | - | - | - | - |
$1,248 21,688 kWh |
$720 212 kW-months/year |
$(-110) - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,575 Cost: $530 |
- | - | - | - | - | - | $1,575 | 534 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$1,575 534 MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $878 Cost: $611 |
- | - | - | - | - | - | $878 | 120 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$878 120 MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $836 Cost: $306 |
$691 | 12,016 | $206 | 61 | $(-61) | - | - | - | - | - | - | - | - | - |
$691 12,016 kWh |
$206 61 kW-months/year |
$(-61) - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $713 Cost: $290 |
$663 | 23,154 | $108 | 32 | $(-58) | - | - | - | - | - | - | - | - | - |
$663 23,154 kWh |
$108 32 kW-months/year |
$(-58) - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $2,820 Cost: $580 |
$2,560 | 44,549 | $485 | 143 | $(-225) | - | - | - | - | - | - | - | - | - |
$2,560 44,549 kWh |
$485 143 kW-months/year |
$(-225) - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $252 Cost: $150 |
$253 | 3,224 | - | - | $(-1) | - | - | - | - | - | - | - | - | - |
$253 3,224 kWh |
- - kW-months/year |
$(-1) - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE |
Savings: $326 Cost: - |
- | - | - | - | - | - | - | - | $326 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$326 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $129,993 Cost: $113,670 |
- | - | - | - | - | - | $27,193 | 9,218 | - | - | $78,000 | - | $24,800 | - |
- - kWh |
- - kW-months/year |
- - $ |
$27,193 9,218 MMBtu |
- - $ |
$78,000 - $ |
$24,800 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 3.5242 RECOVER METALS FROM SPENT SOLUTIONS AND RECYCLE |
Savings: $1,500 Cost: - |
- | - | - | - | - | - | - | - | $1,500 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$1,500 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $152,497 Cost: $141,589 |
$5,687 | 109,320 | $1,519 | 448 | $4,532 | - | $36,133 | 12,071 | $1,826 | - | $78,000 | - | $24,800 | - | $5,687 109,320 kWh |
$1,519 448 kW-months/year |
$4,532 - $ |
$36,133 12,071 MMBtu |
$1,826 - $ |
$78,000 - $ |
$24,800 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $2,942 Cost: $3,558 |
$2,211 | 38,393 | $926 | 273 | $(-195) | - | - | - | - | - | - | - | - | - | $2,211 38,393 kWh |
$926 273 kW-months/year |
$(-195) - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Administrative Changes | Primary Product | By-product Production | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Administrative Changes | Primary Product | By-product Production |