IAC Assessment: OD0037
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OD0037
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Old Dominion Univ.
Assessment Year 1995
Principal Product Paper Converting
NAICS n/a
SIC 2679 - Converted Paper Products, Nec
Sales $10,000,000-$50,000,000
# of Employees 150
Plant Area (Sq.Ft.) 200,000
Annual Production 108,000,000 Pounds
Production Hrs. Annual 6,120
Location (State) VA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $104,687 1,767,585 kWh $0.06
Fuel Oil #2 $14,309 3,920 MMBtu $3.65
TOTAL ENERGY COSTS $118,996
RECOMMENDED SAVINGS* $13,328 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $8,462
#|Description Savings
Cost
Status Electricity Usage Fuel Oil #2 Electricity Usage Fuel Oil #2
$ kWh $ MMBtu
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,053
Cost:
$726
$4,053 68,288 - - $4,053
68,288
kWh
-
-
MMBtu
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$2,607
Cost:
$635
- - $2,607 660 -
-
kWh
$2,607
660
MMBtu
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$612
Cost:
$748
$612 10,258 - - $612
10,258
kWh
-
-
MMBtu
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$720
Cost:
$1,035
$720 12,016 - - $720
12,016
kWh
-
-
MMBtu
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,883
Cost:
$480
$1,883 31,946 - - $1,883
31,946
kWh
-
-
MMBtu
06: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$545
Cost:
$433
$545 9,086 - - $545
9,086
kWh
-
-
MMBtu
07: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$477
Cost:
-
$477 8,206 - - $477
8,206
kWh
-
-
MMBtu
08: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$994
Cost:
-
$994 - - - $994
-
kWh
-
-
MMBtu
09: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$1,437
Cost:
$910
$1,437 24,326 - - $1,437
24,326
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$13,328
Cost:
$4,967
$10,721 164,126 $2,607 660 $10,721
164,126
kWh
$2,607
660
MMBtu
TOTAL IMPLEMENTED Savings:
$8,462
Cost:
$2,864
$8,462 143,024 - - $8,462
143,024
kWh
-
-
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Fuel Oil #2 Electricity Usage Fuel Oil #2