IAC Assessment: OK0073
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0073
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 1983
Principal Product ICE CREAM AND MILK
NAICS n/a
SIC 2026 - Fluid Milk
Sales $10,000,000-$50,000,000
# of Employees 200
Plant Area (Sq.Ft.) 0
Annual Production 131,000 Thousand Gallons
Production Hrs. Annual 5,775
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $155,094 4,140,094 kWh $0.04
Natural Gas $108,065 35,746 MMBtu $3.02
TOTAL ENERGY COSTS $263,159
RECOMMENDED SAVINGS* $85,647 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $59,590
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$433
Cost:
$759
- - $433 134 -
-
kWh
$433
134
MMBtu
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$5,050
Cost:
$8,000
- - $5,050 1,566 -
-
kWh
$5,050
1,566
MMBtu
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$1,010
Cost:
$423
- - $1,010 331 -
-
kWh
$1,010
331
MMBtu
04: 2.7226 USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE Savings:
$2,821
Cost:
$3,032
$2,821 82,943 - - $2,821
82,943
kWh
-
-
MMBtu
05: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$5,161
Cost:
$695
- - $5,161 1,600 -
-
kWh
$5,161
1,600
MMBtu
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,873
Cost:
$4,897
$1,873 48,359 - - $1,873
48,359
kWh
-
-
MMBtu
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$643
Cost:
$1,765
$643 17,292 - - $643
17,292
kWh
-
-
MMBtu
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$333
Cost:
$1,117
$333 11,137 - - $333
11,137
kWh
-
-
MMBtu
09: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$2,659
Cost:
$490
$2,659 75,029 - - $2,659
75,029
kWh
-
-
MMBtu
10: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$4,063
Cost:
$270
- - $4,063 470 -
-
kWh
$4,063
470
MMBtu
11: 2.2447 HEAT WATER WITH EXHAUST HEAT Savings:
$54,540
Cost:
$36,000
- - $54,540 16,909 -
-
kWh
$54,540
16,909
MMBtu
12: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$6,511
Cost:
$27,000
$6,511 - - - $6,511
-
kWh
-
-
MMBtu
13: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC Savings:
$471
Cost:
$477
- - $471 146 -
-
kWh
$471
146
MMBtu
14: 2.2122 INSTALL / REPAIR INSULATION ON CONDENSATE LINES Savings:
$79
Cost:
$136
- - $79 25 -
-
kWh
$79
25
MMBtu
TOTAL RECOMMENDED Savings:
$85,647
Cost:
$85,061
$14,840 234,760 $70,807 21,181 $14,840
234,760
kWh
$70,807
21,181
MMBtu
TOTAL IMPLEMENTED Savings:
$59,590
Cost:
$44,000
- - $59,590 18,475 -
-
kWh
$59,590
18,475
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas