IAC Assessment: OR0116
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1991
Principal Product CONDENSED SKIM MILK
NAICS n/a
SIC 2023 - Dry, Condensed, Evaporated Products
Sales $1,000,000-$5,000,000
# of Employees 10
Plant Area (Sq.Ft.) 0
Annual Production 46,000,000 Pounds
Production Hrs. Annual 3,640
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $28,136 566,823 kWh $0.05
Fuel Oil #2 $130,951 24,220 MMBtu $5.41
TOTAL ENERGY COSTS $159,087
RECOMMENDED SAVINGS* $26,495 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $24,015
#|Description Savings
Cost
Status Electricity Usage Fuel Oil #2 Administrative Changes Electricity Usage Fuel Oil #2 Administrative Changes
$ kWh $ MMBtu $ $
01: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$9,056
Cost:
$776
- - $9,056 1,677 - - -
-
kWh
$9,056
1,677
MMBtu
-
-
$
02: 3.4151 MINIMIZE WATER USAGE Savings:
$1,728
Cost:
-
- - - - $1,728 - -
-
kWh
-
-
MMBtu
$1,728
-
$
03: 2.2447 HEAT WATER WITH EXHAUST HEAT Savings:
$11,470
Cost:
$4,720
- - $11,470 2,128 - - -
-
kWh
$11,470
2,128
MMBtu
-
-
$
04: 2.2123 INSULATE FEEDWATER TANK Savings:
$323
Cost:
$1,804
- - $323 60 - - -
-
kWh
$323
60
MMBtu
-
-
$
05: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$752
Cost:
-
- - - - $752 - -
-
kWh
-
-
MMBtu
$752
-
$
06: 2.2511 INSULATE BARE EQUIPMENT Savings:
$226
Cost:
$491
- - $226 42 - - -
-
kWh
$226
42
MMBtu
-
-
$
07: 2.2444 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS Savings:
$2,781
Cost:
$6,670
- - $2,781 516 - - -
-
kWh
$2,781
516
MMBtu
-
-
$
08: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$118
Cost:
$305
$118 2,345 - - - - $118
2,345
kWh
-
-
MMBtu
-
-
$
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$41
Cost:
-
$79 2,052 - - $(-38) - $79
2,052
kWh
-
-
MMBtu
$(-38)
-
$
TOTAL RECOMMENDED Savings:
$26,495
Cost:
$14,766
$197 4,397 $23,856 4,423 $2,442 - $197
4,397
kWh
$23,856
4,423
MMBtu
$2,442
-
$
TOTAL IMPLEMENTED Savings:
$24,015
Cost:
$14,766
$197 4,397 $23,856 4,423 $(-38) - $197
4,397
kWh
$23,856
4,423
MMBtu
$(-38)
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Fuel Oil #2 Administrative Changes Electricity Usage Fuel Oil #2 Administrative Changes