Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 1995 |
Principal Product | Snowboards |
NAICS | n/a |
SIC | 3949 - Sporting And Athletic Goods, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 350 |
Plant Area (Sq.Ft.) | 118,000 |
Annual Production | 80,031 Pieces |
Production Hrs. Annual | 5,400 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $83,385 | 2,966,882 | kWh | $0.03 |
Natural Gas | $9,184 | 1,732 | MMBtu | $5.30 |
TOTAL ENERGY COSTS | $157,356 | |||
RECOMMENDED SAVINGS* | $29,741 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $17,001 |
#|Description |
Savings Cost |
Status | Electricity Usage | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Solid Waste (non-haz) | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,876 Cost: $8,563 |
$1,821 | 33,998 | - | - | $55 | - |
$1,821 33,998 kWh |
- - lb |
$55 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $895 Cost: $1,734 |
$895 | 16,706 | - | - | - | - |
$895 16,706 kWh |
- - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.1192 REDUCE SCRAP PRODUCTION |
Savings: $12,740 Cost: - |
- | - | $12,740 | 7,400 | - | - |
- - kWh |
$12,740 7,400 lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS |
Savings: $14,230 Cost: - |
- | - | $14,230 | - | - | - |
- - kWh |
$14,230 - lb |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $29,741 Cost: $10,297 |
$2,716 | 50,704 | $26,970 | 7,400 | $55 | - | $2,716 50,704 kWh |
$26,970 7,400 lb |
$55 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $17,001 Cost: $10,297 |
$2,716 | 50,704 | $14,230 | - | $55 | - | $2,716 50,704 kWh |
$14,230 - lb |
$55 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Solid Waste (non-haz) | Personnel Changes | Electricity Usage | Solid Waste (non-haz) | Personnel Changes |