Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2003 |
Principal Product | Canned Beans, Soup |
NAICS | 311422 - Specialty Canning |
SIC | 2032 - Canned Specialties |
Sales | $10,000,000-$50,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 40,000,000 Pieces |
Production Hrs. Annual | 0 |
Location (State) | ID |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $210,307 | 7,183,129 | kWh | $0.03 |
Electricity Demand | $55,186 | 191,700 | kW-months/year | $0.29 |
Electricity Fees | $14,303 | - | $ | - |
Natural Gas | $860,719 | 165,377 | MMBtu | $5.20 |
TOTAL ENERGY COSTS | $1,809,838 | |||
RECOMMENDED SAVINGS* | $370,250 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $353,650 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Energy | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Energy | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.3128 UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS |
Savings: $330,000 Cost: $790,000 |
$(-20,000) | (-650,000) | - | - | - | - | - | - | $350,000 | 350,000 | - | - | - | - |
$(-20,000) (-650,000) kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
$350,000 350,000 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2121 INCREASE AMOUNT OF CONDENSATE RETURNED |
Savings: $13,400 Cost: $28,000 |
- | - | - | - | $13,400 | 2,660 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$13,400 2,660 MMBtu |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1133 ADJUST BURNERS FOR EFFICIENT OPERATION |
Savings: $10,500 Cost: $450 |
- | - | - | - | $11,400 | 2,250 | - | - | - | - | $(-900) | - | - | - |
- - kWh |
- - kW-months/year |
$11,400 2,250 MMBtu |
- - MMBtu |
- - lb |
$(-900) - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $4,500 Cost: $1,850 |
- | - | - | - | - | - | $4,500 | 890 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$4,500 890 MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $5,400 Cost: $12,100 |
$4,280 | 147,000 | $1,120 | 328 | - | - | - | - | - | - | - | - | - | - |
$4,280 147,000 kWh |
$1,120 328 kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2161 OPTIMIZE OPERATION OF MULTI-STAGE VACUUM STEAM JETS |
Savings: $3,250 Cost: $3,000 |
- | - | - | - | - | - | - | - | - | - | - | - | $3,250 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
$3,250 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,940 Cost: $1,850 |
$782 | 26,900 | $264 | 77 | - | - | - | - | - | - | $894 | - | - | - |
$782 26,900 kWh |
$264 77 kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
$894 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $1,260 Cost: $495 |
$1,000 | 34,400 | $260 | 76 | - | - | - | - | - | - | - | - | - | - |
$1,000 34,400 kWh |
$260 76 kW-months/year |
- - MMBtu |
- - MMBtu |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $370,250 Cost: $837,745 |
$(-13,938) | (-441,700) | $1,644 | 481 | $24,800 | 4,910 | $4,500 | 890 | $350,000 | 350,000 | $(-6) | - | $3,250 | - | $(-13,938) (-441,700) kWh |
$1,644 481 kW-months/year |
$24,800 4,910 MMBtu |
$4,500 890 MMBtu |
$350,000 350,000 lb |
$(-6) - $ |
$3,250 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $353,650 Cost: $807,400 |
$(-15,720) | (-503,000) | $1,120 | 328 | $11,400 | 2,250 | $4,500 | 890 | $350,000 | 350,000 | $(-900) | - | $3,250 | - | $(-15,720) (-503,000) kWh |
$1,120 328 kW-months/year |
$11,400 2,250 MMBtu |
$4,500 890 MMBtu |
$350,000 350,000 lb |
$(-900) - $ |
$3,250 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Energy | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Energy | Solid Waste (non-haz) | Administrative Changes | Ancillary Material Cost |