Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Rutgers, State Univ. of NJ |
---|---|
Assessment Year | 1992 |
Principal Product | DIE CAST MOLDS |
NAICS | n/a |
SIC | 3544 - Special Dies, Tools, Jigs & Fixtures |
Sales | $10,000,000-$50,000,000 |
# of Employees | 160 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 7,000 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | NJ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $250,612 | 2,654,455 | kWh | $0.09 |
Natural Gas | $18,053 | 2,690 | MMBtu | $6.71 |
TOTAL ENERGY COSTS | $268,665 | |||
RECOMMENDED SAVINGS* | $31,125 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $5,214 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,359 Cost: $5,963 |
$4,342 | 46,014 | - | - | $(-983) | - |
$4,342 46,014 kWh |
- - MMBtu |
$(-983) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $650 Cost: $500 |
- | - | $650 | 97 | - | - |
- - kWh |
$650 97 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $1,855 Cost: $930 |
- | - | $1,855 | 277 | - | - |
- - kWh |
$1,855 277 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7494 INSTALL STORM WINDOWS AND DOORS |
Savings: $508 Cost: $1,100 |
- | - | $508 | 76 | - | - |
- - kWh |
$508 76 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $6,177 Cost: $2,500 |
$6,177 | - | - | - | - | - |
$6,177 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $4,275 Cost: $2,098 |
$4,275 | 45,428 | - | - | - | - |
$4,275 45,428 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4312 IMPROVE LUBRICATION PRACTICES |
Savings: $10,595 Cost: $800 |
$10,595 | 112,837 | - | - | - | - |
$10,595 112,837 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $3,706 Cost: $4,000 |
$3,706 | - | - | - | - | - |
$3,706 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $31,125 Cost: $17,891 |
$29,095 | 204,279 | $3,013 | 450 | $(-983) | - | $29,095 204,279 kWh |
$3,013 450 MMBtu |
$(-983) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $5,214 Cost: $6,893 |
$4,342 | 46,014 | $1,855 | 277 | $(-983) | - | $4,342 46,014 kWh |
$1,855 277 MMBtu |
$(-983) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |