Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 2000 |
Principal Product | personal hygiene products |
NAICS | n/a |
SIC | 2834 - Pharmaceutical Preparations |
Sales | $10,000,000-$50,000,000 |
# of Employees | 435 |
Plant Area (Sq.Ft.) | 650,000 |
Annual Production | 25,000 Tons |
Production Hrs. Annual | 7,200 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $126,435 | 5,186,987 | kWh | $0.02 |
Electricity Demand | $91,155 | 9,659 | kW-months/year | $9.44 |
Electricity Fees | $1,920 | - | $ | - |
Natural Gas | $173,005 | 47,687 | MMBtu | $3.63 |
TOTAL ENERGY COSTS | $468,371 | |||
RECOMMENDED SAVINGS* | $400,474 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $129,234 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2121 INCREASE AMOUNT OF CONDENSATE RETURNED |
Savings: $36,908 Cost: $85,000 |
- | - | - | - | $29,150 | 8,097 | $7,758 | 7,200,000 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$29,150 8,097 MMBtu |
$7,758 7,200,000 Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $12,800 Cost: $40,000 |
$7,027 | 288,101 | $10,195 | 1,080 | $(-4,422) | (-1,228) | - | - | - | - | - | - | - | - |
$7,027 288,101 kWh |
$10,195 1,080 kW-months/year |
$(-4,422) (-1,228) MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2427 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS |
Savings: $9,331 Cost: $20,000 |
- | - | - | - | $9,331 | 2,592 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$9,331 2,592 MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,867 Cost: $200 |
$3,567 | 146,249 | $2,300 | 243 | - | - | - | - | - | - | - | - | - | - |
$3,567 146,249 kWh |
$2,300 243 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY |
Savings: $4,167 Cost: $10,200 |
$1,467 | 60,082 | $2,700 | 286 | - | - | - | - | - | - | - | - | - | - |
$1,467 60,082 kWh |
$2,700 286 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $2,692 Cost: $1,500 |
$2,692 | 110,492 | - | - | - | - | - | - | - | - | - | - | - | - |
$2,692 110,492 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7145 INSTALL SKYLIGHTS |
Savings: $70,269 Cost: $5,536 |
- | - | $1,269 | 134 | - | - | - | - | - | - | - | - | $69,000 | - |
- - kWh |
$1,269 134 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
$69,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $2,240 Cost: $30,000 |
- | - | - | - | - | - | - | - | - | - | $2,240 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
$2,240 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.112 REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL |
Savings: $256,200 Cost: $100,000 |
- | - | - | - | - | - | - | - | $256,200 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$256,200 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $400,474 Cost: $292,436 |
$14,753 | 604,924 | $16,464 | 1,743 | $34,059 | 9,461 | $7,758 | 7,200,000 | $256,200 | - | $2,240 | - | $69,000 | - | $14,753 604,924 kWh |
$16,464 1,743 kW-months/year |
$34,059 9,461 MMBtu |
$7,758 7,200,000 Tgal |
$256,200 - $ |
$2,240 - $ |
$69,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $129,234 Cost: $122,436 |
$7,726 | 316,823 | $6,269 | 663 | $38,481 | 10,689 | $7,758 | 7,200,000 | - | - | - | - | $69,000 | - | $7,726 316,823 kWh |
$6,269 663 kW-months/year |
$38,481 10,689 MMBtu |
$7,758 7,200,000 Tgal |
- - $ |
- - $ |
$69,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes | Ancillary Material Cost |