IAC Assessment: ST0048
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: ST0048
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Stevens Institute of Technology
Assessment Year 1985
Principal Product PRINTING & BINDING
NAICS n/a
SIC 2741 - Miscellaneous Publishing
Sales $10,000,000-$50,000,000
# of Employees 290
Plant Area (Sq.Ft.) 0
Annual Production 4,000,000 Pieces
Production Hrs. Annual 6,000
Location (State) NJ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $163,048 1,971,864 kWh $0.08
Natural Gas $18,347 2,528 MMBtu $7.26
TOTAL ENERGY COSTS $181,395
RECOMMENDED SAVINGS* $29,858 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $17,955
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes
$ kWh $ MMBtu $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$8,259
Cost:
$735
$8,259 99,941 - - - - $8,259
99,941
kWh
-
-
MMBtu
-
-
$
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$7,750
Cost:
$56
$7,750 93,787 - - - - $7,750
93,787
kWh
-
-
MMBtu
-
-
$
03: 2.6121 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED Savings:
$1,126
Cost:
-
$920 11,137 $206 29 - - $920
11,137
kWh
$206
29
MMBtu
-
-
$
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$485
Cost:
$2,598
$485 5,862 - - - - $485
5,862
kWh
-
-
MMBtu
-
-
$
05: 2.4312 IMPROVE LUBRICATION PRACTICES Savings:
$102
Cost:
-
$702 8,499 - - $(-600) - $702
8,499
kWh
-
-
MMBtu
$(-600)
-
$
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$339
Cost:
$675
$339 4,103 - - - - $339
4,103
kWh
-
-
MMBtu
-
-
$
07: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA Savings:
$4,311
Cost:
-
$4,311 52,169 - - - - $4,311
52,169
kWh
-
-
MMBtu
-
-
$
08: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS Savings:
$335
Cost:
$22
- - $335 47 - - -
-
kWh
$335
47
MMBtu
-
-
$
09: 2.7229 AIR CONDITION ONLY SPACE NECESSARY Savings:
$2,371
Cost:
$700
- - $2,371 333 - - -
-
kWh
$2,371
333
MMBtu
-
-
$
10: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$1,899
Cost:
$2,500
$3,003 36,342 $(-1,104) (-155) - - $3,003
36,342
kWh
$(-1,104)
(-155)
MMBtu
-
-
$
11: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$2,881
Cost:
$440
- - $2,881 405 - - -
-
kWh
$2,881
405
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$29,858
Cost:
$7,726
$25,769 311,840 $4,689 659 $(-600) - $25,769
311,840
kWh
$4,689
659
MMBtu
$(-600)
-
$
TOTAL IMPLEMENTED Savings:
$17,955
Cost:
$3,411
$17,414 210,727 $541 76 - - $17,414
210,727
kWh
$541
76
MMBtu
-
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes