Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Stevens Institute of Technology |
---|---|
Assessment Year | 1986 |
Principal Product | COMPONENTS FOR ELEC EQUIPMENT |
NAICS | n/a |
SIC | 3621 - Motors And Generators |
Sales | $10,000,000-$50,000,000 |
# of Employees | 199 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 60,000 Pieces |
Production Hrs. Annual | 2,000 |
Location (State) | PA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $238,379 | 3,165,885 | kWh | $0.08 |
Natural Gas | $26,264 | 3,208 | MMBtu | $8.19 |
TOTAL ENERGY COSTS | $264,643 | |||
RECOMMENDED SAVINGS* | $103,605 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $27,563 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $2,389 Cost: $1,400 |
$2,389 | 31,653 | - | - |
$2,389 31,653 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,035 Cost: - |
$1,035 | 13,775 | - | - |
$1,035 13,775 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $148 Cost: $100 |
$148 | 2,052 | - | - |
$148 2,052 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $63,655 Cost: $200,000 |
$111,337 | 1,479,191 | $(-47,682) | (-5,938) |
$111,337 1,479,191 kWh |
$(-47,682) (-5,938) MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $12,141 Cost: $40,000 |
$21,425 | 284,584 | $(-9,284) | (-1,156) |
$21,425 284,584 kWh |
$(-9,284) (-1,156) MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $18,041 Cost: - |
$18,041 | 239,742 | - | - |
$18,041 239,742 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $5,537 Cost: $1,000 |
$5,537 | 73,564 | - | - |
$5,537 73,564 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $65 Cost: $200 |
$65 | 879 | - | - |
$65 879 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $181 Cost: $160 |
$181 | 2,345 | - | - |
$181 2,345 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $413 Cost: - |
$413 | 5,569 | - | - |
$413 5,569 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $103,605 Cost: $242,860 |
$160,571 | 2,133,354 | $(-56,966) | (-7,094) | $160,571 2,133,354 kWh |
$(-56,966) (-7,094) MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $27,563 Cost: $2,500 |
$27,563 | 366,355 | - | - | $27,563 366,355 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |