Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Texas, Arlington |
---|---|
Assessment Year | 2006 |
Principal Product | Turbine Engine Blades |
NAICS | 336412 - Aircraft Engine and Engine Parts Manufacturing |
SIC | 3724 - Aircraft Engines And Engine Parts |
Sales | $10,000,000-$50,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 1,000,000 Pieces |
Production Hrs. Annual | 6,312 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $975,676 | 43,561 | kWh | $22.40 |
Electricity Demand | $166,897 | 36,064 | kW-months/year | $4.63 |
Natural Gas | $166,316 | 43,354 | MMBtu | $3.84 |
TOTAL ENERGY COSTS | $1,308,889 | |||
RECOMMENDED SAVINGS* | $49,435 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $36,030 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $18,180 Cost: $16 |
$18,180 | 293,270 | - | - |
$18,180 293,270 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $9,225 Cost: $60 |
$9,225 | 148,880 | - | - |
$9,225 148,880 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY |
Savings: $4,180 Cost: $630 |
$3,700 | 59,830 | $480 | 112 |
$3,700 59,830 kWh |
$480 112 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,450 Cost: $120 |
$2,240 | 36,072 | $210 | 49 |
$2,240 36,072 kWh |
$210 49 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $15,400 Cost: - |
$13,700 | 221,197 | $1,700 | 413 |
$13,700 221,197 kWh |
$1,700 413 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $49,435 Cost: $826 |
$47,045 | 759,249 | $2,390 | 574 | $47,045 759,249 kWh |
$2,390 574 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $36,030 Cost: $136 |
$34,120 | 550,539 | $1,910 | 462 | $34,120 550,539 kWh |
$1,910 462 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand |