IAC logo
IAC Assessment: TN0672
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: TN0672
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Tennessee
Assessment Year 2000
Principal Product Hermetic motors
NAICS n/a
SIC 3621 - Motors And Generators
Sales $50,000,000-$100,000,000
# of Employees 400
Plant Area (Sq.Ft.) 200,000
Annual Production 5,000,000 Pieces
Production Hrs. Annual 8,400
Location (State) TN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $796,768 19,556,565 kWh $0.04
Electricity Demand $205,980 36,492 kW-months/year $5.64
Electricity Fees $102,299 - $ -
LPG $450,984 52,149 MMBtu $8.65
TOTAL ENERGY COSTS $1,556,031
RECOMMENDED SAVINGS* $187,631 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand LPG Solid Waste (non-haz) Personnel Changes Increase in Production Electricity Usage Electricity Demand LPG Solid Waste (non-haz) Personnel Changes Increase in Production
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ %
01: 4.4230 MOVE PRODUCT USING MECHANICAL MEANS Savings:
$65,150
Cost:
$167,200
- - - - - - - - $58,750 - $6,400 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
$58,750
-
$
$6,400
-
%
02: 3.7135 MINIMIZE USE OF RAGS THROUGH WORKER TRAINING Savings:
$30,000
Cost:
-
- - - - - - $30,000 1,500 - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$30,000
1,500
lb
-
-
$
-
-
%
03: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER Savings:
$18,266
Cost:
$27,000
$7,967 195,487 $10,299 1,646 - - - - - - - - $7,967
195,487
kWh
$10,299
1,646
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
%
04: 2.2628 UTILIZE A LESS EXPENSIVE COOLING METHOD Savings:
$14,770
Cost:
$17,800
$14,770 293,083 - - - - - - - - - - $14,770
293,083
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
%
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$13,010
Cost:
$1,650
$13,010 241,794 - - - - - - - - - - $13,010
241,794
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
%
06: 2.7245 USE DIRECT AIR SUPPLY TO EXHAUST HOODS Savings:
$8,990
Cost:
$19,000
$8,990 167,057 - - - - - - - - - - $8,990
167,057
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
%
07: 3.7214 REDUCE OR ELIMINATE WASTE Savings:
$8,100
Cost:
$3,650
- - - - - - $8,100 4,050 - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$8,100
4,050
lb
-
-
$
-
-
%
08: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$7,385
Cost:
$13,750
- - - - $7,385 683 - - - - - - -
-
kWh
-
-
kW-months/year
$7,385
683
MMBtu
-
-
lb
-
-
$
-
-
%
09: 2.2514 COVER OPEN TANKS Savings:
$7,260
Cost:
$1,500
$7,260 134,818 - - - - - - - - - - $7,260
134,818
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
%
10: 2.1113 REDUCE COMBUSTION AIR FLOW TO OPTIMUM Savings:
$6,380
Cost:
$13,800
$6,380 216,002 - - - - - - - - - - $6,380
216,002
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
%
11: 2.4314 USE SYNTHETIC LUBRICANT Savings:
$3,630
Cost:
-
$1,420 61,547 $2,210 204 - - - - - - - - $1,420
61,547
kWh
$2,210
204
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
%
12: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$2,770
Cost:
$1,440
$1,080 38,101 $1,690 156 - - - - - - - - $1,080
38,101
kWh
$1,690
156
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
%
13: 2.5195 CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS Savings:
$1,920
Cost:
$5,000
$1,920 44,549 - - - - - - - - - - $1,920
44,549
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
%
TOTAL RECOMMENDED Savings:
$187,631
Cost:
$271,790
$62,797 1,392,438 $14,199 2,006 $7,385 683 $38,100 5,550 $58,750 - $6,400 - $62,797
1,392,438
kWh
$14,199
2,006
kW-months/year
$7,385
683
MMBtu
$38,100
5,550
lb
$58,750
-
$
$6,400
-
%
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
-
-
%
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $ $ %
Electricity Usage Electricity Demand LPG Solid Waste (non-haz) Personnel Changes Increase in Production Electricity Usage Electricity Demand LPG Solid Waste (non-haz) Personnel Changes Increase in Production