IAC Assessment: UD0229
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0229
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 1987
Principal Product CHEM. REAGENTS& SOLVENTS
NAICS n/a
SIC 2869 - Industrial Organic Chemicals, Nec
Sales $10,000,000-$50,000,000
# of Employees 120
Plant Area (Sq.Ft.) 0
Annual Production 0 Units
Production Hrs. Annual 4,000
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $147,574 2,600,528 kWh $0.06
Natural Gas $172,856 41,802 MMBtu $4.14
TOTAL ENERGY COSTS $320,430
RECOMMENDED SAVINGS* $24,776 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $24,776
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes
$ kWh $ MMBtu $ $
01: 2.5194 REDESIGN PROCESS Savings:
$3,516
Cost:
-
$(-1,021) (-2,931) $4,177 1,305 $360 - $(-1,021)
(-2,931)
kWh
$4,177
1,305
MMBtu
$360
-
$
02: 2.2121 INCREASE AMOUNT OF CONDENSATE RETURNED Savings:
$7,735
Cost:
$2,000
- - $6,475 2,024 $1,260 - -
-
kWh
$6,475
2,024
MMBtu
$1,260
-
$
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$6,624
Cost:
$6,000
- - $6,624 2,070 - - -
-
kWh
$6,624
2,070
MMBtu
-
-
$
04: 2.2122 INSTALL / REPAIR INSULATION ON CONDENSATE LINES Savings:
$1,125
Cost:
$935
- - $1,125 351 - - -
-
kWh
$1,125
351
MMBtu
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$5,776
Cost:
$20,400
$2,322 32,532 $(-228) (-71) $3,682 - $2,322
32,532
kWh
$(-228)
(-71)
MMBtu
$3,682
-
$
TOTAL RECOMMENDED Savings:
$24,776
Cost:
$29,335
$1,301 29,601 $18,173 5,679 $5,302 - $1,301
29,601
kWh
$18,173
5,679
MMBtu
$5,302
-
$
TOTAL IMPLEMENTED Savings:
$24,776
Cost:
$29,335
$1,301 29,601 $18,173 5,679 $5,302 - $1,301
29,601
kWh
$18,173
5,679
MMBtu
$5,302
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes