Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 1989 |
Principal Product | NEWSPAPER INSERTS |
NAICS | n/a |
SIC | 2711 - Newspapers |
Sales | $10,000,000-$50,000,000 |
# of Employees | 245 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 2,147,483,647 Pieces |
Production Hrs. Annual | 8,400 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $298,445 | 6,177,609 | kWh | $0.05 |
Natural Gas | $142,310 | 35,121 | MMBtu | $4.05 |
TOTAL ENERGY COSTS | $440,755 | |||
RECOMMENDED SAVINGS* | $19,286 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $14,177 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY |
Savings: $3,249 Cost: $300 |
$3,481 | 88,511 | $(-232) | (-59) | - | - |
$3,481 88,511 kWh |
$(-232) (-59) MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $1,466 Cost: - |
$3,066 | - | - | - | $(-1,600) | - |
$3,066 - kWh |
- - MMBtu |
$(-1,600) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $799 Cost: $500 |
$799 | 36,342 | - | - | - | - |
$799 36,342 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3511 USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS |
Savings: $10,928 Cost: $28,000 |
$13,428 | - | - | - | $(-2,500) | - |
$13,428 - kWh |
- - MMBtu |
$(-2,500) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,844 Cost: $15,120 |
$2,870 | 70,633 | $(-626) | (-161) | $600 | - |
$2,870 70,633 kWh |
$(-626) (-161) MMBtu |
$600 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $19,286 Cost: $43,920 |
$23,644 | 195,486 | $(-858) | (-220) | $(-3,500) | - | $23,644 195,486 kWh |
$(-858) (-220) MMBtu |
$(-3,500) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $14,177 Cost: $28,300 |
$16,909 | 88,511 | $(-232) | (-59) | $(-2,500) | - | $16,909 88,511 kWh |
$(-232) (-59) MMBtu |
$(-2,500) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |