Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2008 |
Principal Product | automotive shift towers and control cables |
NAICS | 336320 - Motor Vehicle Electrical and Electronic Equipment Manufacturing |
SIC | 3714 - Motor Vehicle Parts And Accessories |
Sales | $50,000,000-$100,000,000 |
# of Employees | 365 |
Plant Area (Sq.Ft.) | 145,000 |
Annual Production | 3,000,000 Pieces |
Production Hrs. Annual | 4,000 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $504,750 | 10,579,200 | kWh | $0.05 |
Natural Gas | $34,711 | 3,015 | MMBtu | $11.51 |
TOTAL ENERGY COSTS | $539,461 | |||
RECOMMENDED SAVINGS* | $127,339 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $26,465 Cost: - |
$26,465 | 1,017,900 | - | - | - | - | - | - | - | - |
$26,465 1,017,900 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $25,926 Cost: $27,004 |
$10,128 | 456,000 | $11,856 | 76 | - | - | - | - | $3,942 | - |
$10,128 456,000 kWh |
$11,856 76 kW-months/year |
- - MMBtu |
- - $ |
$3,942 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $23,572 Cost: $65,625 |
$11,606 | 446,400 | $11,966 | 90 | - | - | - | - | - | - |
$11,606 446,400 kWh |
$11,966 90 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $15,545 Cost: $10,000 |
- | - | - | - | $15,545 | 1,364 | - | - | - | - |
- - kWh |
- - kW-months/year |
$15,545 1,364 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $7,231 Cost: $7,200 |
$3,799 | 42,120 | $2,304 | 17 | - | - | - | - | $1,128 | - |
$3,799 42,120 kWh |
$2,304 17 kW-months/year |
- - MMBtu |
- - $ |
$1,128 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7145 INSTALL SKYLIGHTS |
Savings: $6,996 Cost: $40,770 |
$2,287 | 87,980 | $4,709 | 53 | - | - | - | - | - | - |
$2,287 87,980 kWh |
$4,709 53 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY |
Savings: $5,745 Cost: - |
$1,835 | 70,560 | $3,910 | 29 | - | - | - | - | - | - |
$1,835 70,560 kWh |
$3,910 29 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $4,324 Cost: - |
$1,599 | 61,200 | $2,725 | 20 | - | - | - | - | - | - |
$1,599 61,200 kWh |
$2,725 20 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $3,818 Cost: $5,000 |
- | - | - | - | $3,818 | 337 | - | - | - | - |
- - kWh |
- - kW-months/year |
$3,818 337 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,826 Cost: - |
$936 | 36,000 | $890 | 7 | - | - | - | - | - | - |
$936 36,000 kWh |
$890 7 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,659 Cost: $600 |
$842 | 32,400 | $817 | 6 | - | - | - | - | - | - |
$842 32,400 kWh |
$817 6 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY |
Savings: $1,581 Cost: $500 |
$983 | 37,800 | $598 | 4 | - | - | - | - | - | - |
$983 37,800 kWh |
$598 4 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $970 Cost: $1,000 |
$1,560 | 60,000 | $1,330 | 10 | - | - | $(-960) | - | $(-960) | - |
$1,560 60,000 kWh |
$1,330 10 kW-months/year |
- - MMBtu |
$(-960) - $ |
$(-960) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $844 Cost: $500 |
$312 | 12,000 | $532 | 4 | - | - | - | - | - | - |
$312 12,000 kWh |
$532 4 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
15: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $837 Cost: $400 |
$452 | 17,400 | $385 | 3 | - | - | - | - | - | - |
$452 17,400 kWh |
$385 3 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $127,339 Cost: $158,599 |
$62,804 | 2,377,760 | $42,022 | 319 | $19,363 | 1,701 | $(-960) | - | $4,110 | - | $62,804 2,377,760 kWh |
$42,022 319 kW-months/year |
$19,363 1,701 MMBtu |
$(-960) - $ |
$4,110 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost |