Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Florida |
---|---|
Assessment Year | 1992 |
Principal Product | PRE-STRESSED CONCRETE |
NAICS | n/a |
SIC | 3531 - Construction Machinery |
Sales | $50,000,000-$100,000,000 |
# of Employees | 55 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 59,000 Tons |
Production Hrs. Annual | 7,488 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $440,417 | 6,616,354 | kWh | $0.07 |
LPG | $45,595 | 7,010 | MMBtu | $6.50 |
Fuel Oil #2 | $4,912 | 755 | MMBtu | $6.51 |
TOTAL ENERGY COSTS | $490,924 | |||
RECOMMENDED SAVINGS* | $42,861 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $17,787 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $610 Cost: $642 |
$610 | 9,672 | - | - |
$610 9,672 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP |
Savings: $4,143 Cost: $4,000 |
$4,143 | 57,737 | - | - |
$4,143 57,737 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $267 Cost: $550 |
$267 | 4,103 | - | - |
$267 4,103 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,380 Cost: $4,766 |
$3,380 | 50,410 | - | - |
$3,380 50,410 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $1,445 Cost: $1,200 |
$1,445 | 21,688 | - | - |
$1,445 21,688 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7233 USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT |
Savings: $1,567 Cost: $2,820 |
$1,567 | 23,447 | - | - |
$1,567 23,447 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $10,518 Cost: $49,969 |
$10,518 | 157,093 | - | - |
$10,518 157,093 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $10,050 Cost: - |
$10,050 | - | - | - |
$10,050 - kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $10,881 Cost: $17,195 |
- | - | $10,881 | 1,674 |
- - kWh |
$10,881 1,674 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $42,861 Cost: $81,142 |
$31,980 | 324,150 | $10,881 | 1,674 | $31,980 324,150 kWh |
$10,881 1,674 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $17,787 Cost: $59,947 |
$17,787 | 266,413 | - | - | $17,787 266,413 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |