IAC Assessment: UF0113
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UF0113
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Florida
Assessment Year 1995
Principal Product Wooden Pallets
NAICS n/a
SIC 2448 - Wood Pallets And Skids
Sales $5,000,000-$10,000,000
# of Employees 65
Plant Area (Sq.Ft.) 9,000
Annual Production 1,000,000 Pieces
Production Hrs. Annual 4,498
Location (State) FL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $86,573 761,137 kWh $0.11
TOTAL ENERGY COSTS $86,573
RECOMMENDED SAVINGS* $19,475 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $8,366
#|Description Savings
Cost
Status Electricity Usage Fuel Oil #2 Personnel Changes Administrative Changes Electricity Usage Fuel Oil #2 Personnel Changes Administrative Changes
$ kWh $ MMBtu $ $ $ $
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$5,541
Cost:
$1,000
$5,541 - - - - - - - $5,541
-
kWh
-
-
MMBtu
-
-
$
-
-
$
02: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS Savings:
$4,588
Cost:
$84
- - - - $4,588 - - - -
-
kWh
-
-
MMBtu
$4,588
-
$
-
-
$
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$972
Cost:
$3,690
$972 9,379 - - - - - - $972
9,379
kWh
-
-
MMBtu
-
-
$
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,911
Cost:
$5,465
$1,911 19,930 - - - - - - $1,911
19,930
kWh
-
-
MMBtu
-
-
$
-
-
$
05: 2.7134 USE PHOTOCELL CONTROLS Savings:
$895
Cost:
$1,800
$895 13,482 - - - - - - $895
13,482
kWh
-
-
MMBtu
-
-
$
-
-
$
06: 2.4134 REPLACE ELECTRIC MOTOR WITH FOSSIL FUEL ENGINE Savings:
$5,568
Cost:
$27,500
$15,848 137,163 $(-7,280) (-2,038) - - $(-3,000) - $15,848
137,163
kWh
$(-7,280)
(-2,038)
MMBtu
-
-
$
$(-3,000)
-
$
TOTAL RECOMMENDED Savings:
$19,475
Cost:
$39,539
$25,167 179,954 $(-7,280) (-2,038) $4,588 - $(-3,000) - $25,167
179,954
kWh
$(-7,280)
(-2,038)
MMBtu
$4,588
-
$
$(-3,000)
-
$
TOTAL IMPLEMENTED Savings:
$8,366
Cost:
$11,039
$3,778 42,791 - - $4,588 - - - $3,778
42,791
kWh
-
-
MMBtu
$4,588
-
$
-
-
$
Savings
Cost
$ kWh $ MMBtu $ $ $ $
Electricity Usage Fuel Oil #2 Personnel Changes Administrative Changes Electricity Usage Fuel Oil #2 Personnel Changes Administrative Changes