Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Florida |
---|---|
Assessment Year | 2022 |
Principal Product | Refrigeration Services |
NAICS | 488510 - Freight Transportation Arrangement |
SIC | 4731 - Freight Transportation Arrangement |
Sales | $5,000,000-$10,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 240,000 |
Annual Production | 167,018 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $551,987 | 10,687,346 | kWh | $0.05 |
Electricity Demand | $75,693 | 18,536 | kW-months/year | $4.08 |
Electricity Fees | $95,203 | - | $ | - |
TOTAL ENERGY COSTS | $722,883 | |||
RECOMMENDED SAVINGS* | $477,930 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $85,535 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3417 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT |
Savings: $383,709 Cost: $1,629,000 |
$518,250 | 9,966,338 | $65,460 | 16,028 | $(-115,001) | (-82,863) | $(-85,000) | - |
$518,250 9,966,338 kWh |
$65,460 16,028 kW-months/year |
$(-115,001) (-82,863) MMBtu |
$(-85,000) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $44,200 Cost: $57,498 |
$38,902 | 748,114 | $5,298 | 1,297 | - | - | - | - |
$38,902 748,114 kWh |
$5,298 1,297 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC |
Savings: $18,832 Cost: $31,696 |
$18,832 | 362,161 | - | - | - | - | - | - |
$18,832 362,161 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $11,115 Cost: $20,214 |
$11,115 | 213,747 | - | - | - | - | - | - |
$11,115 213,747 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7425 CLEAN OR COLOR ROOF TO REDUCE SOLAR LOAD |
Savings: $8,686 Cost: $42,931 |
$8,686 | 167,047 | - | - | - | - | - | - |
$8,686 167,047 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $4,465 Cost: $8,588 |
$4,465 | 85,867 | - | - | - | - | - | - |
$4,465 85,867 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $3,037 Cost: $2,270 |
$3,037 | 58,400 | - | - | - | - | - | - |
$3,037 58,400 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,370 Cost: $10,501 |
$1,792 | 34,456 | $578 | 142 | - | - | - | - |
$1,792 34,456 kWh |
$578 142 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,516 Cost: $594 |
$1,342 | 25,802 | $174 | 42 | - | - | - | - |
$1,342 25,802 kWh |
$174 42 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $477,930 Cost: $1,803,292 |
$606,421 | 11,661,932 | $71,510 | 17,510 | $(-115,001) | (-82,863) | $(-85,000) | - | $606,421 11,661,932 kWh |
$71,510 17,510 kW-months/year |
$(-115,001) (-82,863) MMBtu |
$(-85,000) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $85,535 Cost: $131,361 |
$79,485 | 1,528,547 | $6,050 | 1,481 | - | - | - | - | $79,485 1,528,547 kWh |
$6,050 1,481 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |