Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Louisville
Assessment Year 1995
Principal Product Portable Water Storage Tanks
NAICS n/a
SIC 3433 - Heating Equipment, Except Electric
Sales $10,000,000-$50,000,000
# of Employees 110
Plant Area (Sq.Ft.) 180,000
Annual Production 100 Pieces
Production Hrs. Annual 5,000
Location (State) KY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $134,784 2,124,560 kWh $0.06
Natural Gas $63,729 15,172 MMBtu $4.20
TOTAL ENERGY COSTS $397,152
RECOMMENDED SAVINGS* $205,653 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $977
#|Description Savings
Cost
Status Electricity Usage Natural Gas Other Liquid (haz) Solid Waste (non-haz) Solid Waste (haz) Electricity Usage Natural Gas Other Liquid (haz) Solid Waste (non-haz) Solid Waste (haz)
$ kWh $ MMBtu $ gal $ lb $ lb
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,714
Cost:
$1,789
$2,714 42,790 - - - - - - - - $2,714
42,790
kWh
-
-
MMBtu
-
-
gal
-
-
lb
-
-
lb
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$1,134
Cost:
$43
$1,134 17,878 - - - - - - - - $1,134
17,878
kWh
-
-
MMBtu
-
-
gal
-
-
lb
-
-
lb
03: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$848
Cost:
$1,000
- - $848 202 - - - - - - -
-
kWh
$848
202
MMBtu
-
-
gal
-
-
lb
-
-
lb
04: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$977
Cost:
$1,120
$977 - - - - - - - - - $977
-
kWh
-
-
MMBtu
-
-
gal
-
-
lb
-
-
lb
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$2,406
Cost:
$3,609
$2,406 37,808 - - - - - - - - $2,406
37,808
kWh
-
-
MMBtu
-
-
gal
-
-
lb
-
-
lb
06: 3.2172 USE AUTOMATIC CLEANING EQUIPMENT Savings:
$2,033
Cost:
$1,615
- - - - $1,528 501 $505 372 - - -
-
kWh
-
-
MMBtu
$1,528
501
gal
$505
372
lb
-
-
lb
07: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS Savings:
$92,792
Cost:
$17,600
- - - - $89,680 4,720 - - $3,112 3,890 -
-
kWh
-
-
MMBtu
$89,680
4,720
gal
-
-
lb
$3,112
3,890
lb
08: 3.2136 USE "WASH-LESS" PROCESSING EQUIPMENT Savings:
$99,415
Cost:
$9,240
- - - - $96,083 5,057 - - $3,332 4,165 -
-
kWh
-
-
MMBtu
$96,083
5,057
gal
-
-
lb
$3,332
4,165
lb
09: 3.1192 REDUCE SCRAP PRODUCTION Savings:
$3,333
Cost:
$3,124
- - - - - - - - $3,333 4,167 -
-
kWh
-
-
MMBtu
-
-
gal
-
-
lb
$3,333
4,167
lb
10: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE Savings:
$77
Cost:
$75
- - - - - - $1 88 $76 5,058 -
-
kWh
-
-
MMBtu
-
-
gal
$1
88
lb
$76
5,058
lb
11: 3.8143 RECYCLE CLEANING SOLVENT AND REUSE Savings:
$(-76)
Cost:
$89
- - - - - - - - $(-76) 1,293 -
-
kWh
-
-
MMBtu
-
-
gal
-
-
lb
$(-76)
1,293
lb
TOTAL RECOMMENDED Savings:
$205,653
Cost:
$39,304
$7,231 98,476 $848 202 $187,291 10,278 $506 460 $9,777 18,573 $7,231
98,476
kWh
$848
202
MMBtu
$187,291
10,278
gal
$506
460
lb
$9,777
18,573
lb
TOTAL IMPLEMENTED Savings:
$977
Cost:
$1,120
$977 - - - - - - - - - $977
-
kWh
-
-
MMBtu
-
-
gal
-
-
lb
-
-
lb
Savings
Cost
$ kWh $ MMBtu $ gal $ lb $ lb
Electricity Usage Natural Gas Other Liquid (haz) Solid Waste (non-haz) Solid Waste (haz) Electricity Usage Natural Gas Other Liquid (haz) Solid Waste (non-haz) Solid Waste (haz)