Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Louisville |
---|---|
Assessment Year | 1996 |
Principal Product | Wood Office Furniture |
NAICS | n/a |
SIC | 2521 - Wood Office Furniture |
Sales | $10,000,000-$50,000,000 |
# of Employees | 96 |
Plant Area (Sq.Ft.) | 124,635 |
Annual Production | 18,780 Pieces |
Production Hrs. Annual | 5,000 |
Location (State) | IN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $71,984 | 1,109,320 | kWh | $0.06 |
Natural Gas | $24,894 | 5,748 | MMBtu | $4.33 |
TOTAL ENERGY COSTS | $108,299 | |||
RECOMMENDED SAVINGS* | $138,064 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $126,617 |
#|Description |
Savings Cost |
Status | Electricity Usage | Solid Waste (haz) | Administrative Changes | Primary Raw Material | Electricity Usage | Solid Waste (haz) | Administrative Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $489 Cost: $795 |
$489 | 7,620 | - | - | - | - | - | - |
$489 7,620 kWh |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $135 Cost: $40 |
$135 | 2,052 | - | - | - | - | - | - |
$135 2,052 kWh |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $197 Cost: $3,920 |
$197 | 2,931 | - | - | - | - | - | - |
$197 2,931 kWh |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $11,447 Cost: - |
- | - | $267 | 10,400 | $5,200 | - | $5,980 | - |
- - kWh |
$267 10,400 lb |
$5,200 - $ |
$5,980 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $125,796 Cost: $67,000 |
- | - | $218 | 11,716 | $8,401 | - | $117,177 | - |
- - kWh |
$218 11,716 lb |
$8,401 - $ |
$117,177 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $138,064 Cost: $71,755 |
$821 | 12,603 | $485 | 22,116 | $13,601 | - | $123,157 | - | $821 12,603 kWh |
$485 22,116 lb |
$13,601 - $ |
$123,157 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $126,617 Cost: $71,755 |
$821 | 12,603 | $218 | 11,716 | $8,401 | - | $117,177 | - | $821 12,603 kWh |
$218 11,716 lb |
$8,401 - $ |
$117,177 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Solid Waste (haz) | Administrative Changes | Primary Raw Material | Electricity Usage | Solid Waste (haz) | Administrative Changes | Primary Raw Material |