IAC logo
IAC Assessment: UL0180
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UL0180
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Louisville
Assessment Year 1997
Principal Product office furniture
NAICS n/a
SIC 2521 - Wood Office Furniture
Sales $10,000,000-$50,000,000
# of Employees 160
Plant Area (Sq.Ft.) 162,576
Annual Production 9,000 Pieces
Production Hrs. Annual 2,250
Location (State) IN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $54,637 1,440,504 kWh $0.04
Electricity Demand $29,478 4,316 kW-months/year $6.83
Natural Gas $16,564 7,539 MMBtu $2.20
TOTAL ENERGY COSTS $108,160
RECOMMENDED SAVINGS* $33,500 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $32,839
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Solid Waste (haz) Administrative Changes Electricity Usage Electricity Demand Solid Waste (non-haz) Solid Waste (haz) Administrative Changes
$ kWh $ kW-months/year $ lb $ lb $ $
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$135
Cost:
$3,650
$69 1,758 $66 10 - - - - - - $69
1,758
kWh
$66
10
kW-months/year
-
-
lb
-
-
lb
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$289
Cost:
$2,813
$161 4,396 $128 19 - - - - - - $161
4,396
kWh
$128
19
kW-months/year
-
-
lb
-
-
lb
-
-
$
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$526
Cost:
$87
$266 7,034 $260 38 - - - - - - $266
7,034
kWh
$260
38
kW-months/year
-
-
lb
-
-
lb
-
-
$
04: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS Savings:
$8,150
Cost:
-
- - - - - - $8,150 10,000 - - -
-
kWh
-
-
kW-months/year
-
-
lb
$8,150
10,000
lb
-
-
$
05: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS Savings:
$5,000
Cost:
$17,500
- - - - $5,000 59,350 - - - - -
-
kWh
-
-
kW-months/year
$5,000
59,350
lb
-
-
lb
-
-
$
06: 4.431 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY Savings:
$19,400
Cost:
$3,600
- - - - - - - - $19,400 - -
-
kWh
-
-
kW-months/year
-
-
lb
-
-
lb
$19,400
-
$
TOTAL RECOMMENDED Savings:
$33,500
Cost:
$27,650
$496 13,188 $454 67 $5,000 59,350 $8,150 10,000 $19,400 - $496
13,188
kWh
$454
67
kW-months/year
$5,000
59,350
lb
$8,150
10,000
lb
$19,400
-
$
TOTAL IMPLEMENTED Savings:
$32,839
Cost:
$23,913
$161 4,396 $128 19 $5,000 59,350 $8,150 10,000 $19,400 - $161
4,396
kWh
$128
19
kW-months/year
$5,000
59,350
lb
$8,150
10,000
lb
$19,400
-
$
Savings
Cost
$ kWh $ kW-months/year $ lb $ lb $ $
Electricity Usage Electricity Demand Solid Waste (non-haz) Solid Waste (haz) Administrative Changes Electricity Usage Electricity Demand Solid Waste (non-haz) Solid Waste (haz) Administrative Changes