Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Michigan |
---|---|
Assessment Year | 1996 |
Principal Product | Automotive Stampings and Assembly |
NAICS | n/a |
SIC | 3469 - Metal Stampings, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 80,000 |
Annual Production | 60,000,000 Pieces |
Production Hrs. Annual | 7,344 |
Location (State) | MI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $346,068 | 11,443,435 | kWh | $0.03 |
Electricity Demand | $338,023 | 28,706 | kW-months/year | $11.78 |
Electricity Fees | $38,942 | - | $ | - |
Natural Gas | $28,674 | 6,758 | MMBtu | $4.24 |
TOTAL ENERGY COSTS | $716,907 | |||
RECOMMENDED SAVINGS* | $44,263 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $3,147 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,573 Cost: $3,037 |
$1,007 | 33,998 | $566 | 56 | - | - | - | - |
$1,007 33,998 kWh |
$566 56 kW-months/year |
- - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $885 Cost: $3,074 |
$338 | 11,430 | $547 | 54 | - | - | - | - |
$338 11,430 kWh |
$547 54 kW-months/year |
- - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $21,041 Cost: $15,570 |
- | - | $16,339 | 1,605 | $4,702 | - | - | - |
- - kWh |
$16,339 1,605 kW-months/year |
$4,702 - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $689 Cost: $1,200 |
$441 | 14,947 | $248 | 21 | - | - | - | - |
$441 14,947 kWh |
$248 21 kW-months/year |
- - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $830 Cost: $960 |
$531 | 17,878 | $299 | 29 | - | - | - | - |
$531 17,878 kWh |
$299 29 kW-months/year |
- - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $10,326 Cost: - |
$6,611 | 223,329 | $3,715 | 365 | - | - | - | - |
$6,611 223,329 kWh |
$3,715 365 kW-months/year |
- - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $5,439 Cost: $24,000 |
- | - | $5,439 | 504 | - | - | - | - |
- - kWh |
$5,439 504 kW-months/year |
- - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $3,480 Cost: $1,200 |
- | - | - | - | - | - | $3,480 | 600,000 |
- - kWh |
- - kW-months/year |
- - $ |
$3,480 600,000 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $44,263 Cost: $49,041 |
$8,928 | 301,582 | $27,153 | 2,634 | $4,702 | - | $3,480 | 600,000 | $8,928 301,582 kWh |
$27,153 2,634 kW-months/year |
$4,702 - $ |
$3,480 600,000 lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $3,147 Cost: $7,311 |
$1,786 | 60,375 | $1,361 | 131 | - | - | - | - | $1,786 60,375 kWh |
$1,361 131 kW-months/year |
- - $ |
- - lb |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Electricity Fees | Solid Waste (non-haz) |