Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Utah
Assessment Year 2006
Principal Product Vegetables
NAICS 311991 - Perishable Prepared Food Manufacturing
SIC 2099 - Food Preparations, Nec
Sales $10,000,000-$50,000,000
# of Employees 185
Plant Area (Sq.Ft.) 80,000
Annual Production 57,000,000 Pounds
Production Hrs. Annual 4,160
Location (State) UT
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $45,620 1,690,011 kWh $0.03
Electricity Demand $50,044 4,647 kW-months/year $10.77
Natural Gas $31,311 4,662 MMBtu $6.72
TOTAL ENERGY COSTS $126,975
RECOMMENDED SAVINGS* $128,560 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Administrative Changes Electricity Usage Electricity Demand Administrative Changes
$ kWh $ kW-months/year $ $
01: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER Savings:
$16,190
Cost:
$10,000
- - $16,190 1,392 - - -
-
kWh
$16,190
1,392
kW-months/year
-
-
$
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,280
Cost:
$4,150
$580 21,860 $700 60 - - $580
21,860
kWh
$700
60
kW-months/year
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,230
Cost:
$3,050
$990 37,190 $1,240 107 - - $990
37,190
kWh
$1,240
107
kW-months/year
-
-
$
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$4,760
Cost:
$10,030
$2,360 89,090 $2,400 206 - - $2,360
89,090
kWh
$2,400
206
kW-months/year
-
-
$
05: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$3,770
Cost:
$4,140
- - $3,770 324 - - -
-
kWh
$3,770
324
kW-months/year
-
-
$
06: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE Savings:
$100,330
Cost:
$52,800
- - - - $100,330 - -
-
kWh
-
-
kW-months/year
$100,330
-
$
TOTAL RECOMMENDED Savings:
$128,560
Cost:
$84,170
$3,930 148,140 $24,300 2,089 $100,330 - $3,930
148,140
kWh
$24,300
2,089
kW-months/year
$100,330
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand Administrative Changes Electricity Usage Electricity Demand Administrative Changes