Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Utah |
---|---|
Assessment Year | 2020 |
Principal Product | Bottled milk, cottage cheese, orange juice |
NAICS | 311511 - Fluid Milk Manufacturing |
SIC | 2026 - Fluid Milk |
Sales | $1,000,000-$5,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 92,350 |
Annual Production | 10,500,000 Pounds |
Production Hrs. Annual | 8,720 |
Location (State) | UT |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $520,234 | 15,818,880 | kWh | $0.03 |
Electricity Demand | $410,617 | 30,215 | kW-months/year | $13.59 |
Electricity Fees | $74,307 | - | $ | - |
Natural Gas | $270,305 | 74,100 | MMBtu | $3.65 |
TOTAL ENERGY COSTS | $2,455,328 | |||
RECOMMENDED SAVINGS* | $192,760 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $111,470 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Usage | Water Disposal | Personnel Changes | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Usage | Water Disposal | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2121 INCREASE AMOUNT OF CONDENSATE RETURNED |
Savings: $47,740 Cost: $212,490 |
- | - | - | - | $(-1,840) | - | $28,990 | 7,950 | $5,650 | 3,740 | $14,940 | 3,740 | - | - |
- - kWh |
- - kW-months/year |
$(-1,840) - $ |
$28,990 7,950 MMBtu |
$5,650 3,740 Tgal |
$14,940 3,740 Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $41,050 Cost: $179,660 |
$26,240 | 795,110 | $14,810 | 1,090 | - | - | - | - | - | - | - | - | - | - |
$26,240 795,110 kWh |
$14,810 1,090 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY |
Savings: $30,330 Cost: $4,800 |
$25,050 | 759,060 | $5,280 | 389 | - | - | - | - | - | - | - | - | - | - |
$25,050 759,060 kWh |
$5,280 389 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4154 ELIMINATE LEAKS IN WATER LINES AND VALVES |
Savings: $14,460 Cost: $13,100 |
- | - | - | - | - | - | - | - | $3,970 | 2,630 | $10,490 | 2,630 | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$3,970 2,630 Tgal |
$10,490 2,630 Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $8,220 Cost: $23,540 |
$5,160 | 156,390 | $3,060 | 225 | - | - | - | - | - | - | - | - | - | - |
$5,160 156,390 kWh |
$3,060 225 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $960 Cost: $1,140 |
$610 | 18,550 | $350 | 26 | - | - | - | - | - | - | - | - | - | - |
$610 18,550 kWh |
$350 26 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.8124 Hire Energy Manager |
Savings: $50,000 Cost: $2,700 |
- | - | - | - | - | - | - | - | - | - | - | - | $50,000 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
$50,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $192,760 Cost: $437,430 |
$57,060 | 1,729,110 | $23,500 | 1,729 | $(-1,840) | - | $28,990 | 7,950 | $9,620 | 6,370 | $25,430 | 6,370 | $50,000 | - | $57,060 1,729,110 kWh |
$23,500 1,729 kW-months/year |
$(-1,840) - $ |
$28,990 7,950 MMBtu |
$9,620 6,370 Tgal |
$25,430 6,370 Tgal |
$50,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $111,470 Cost: $428,790 |
$31,400 | 951,500 | $17,870 | 1,315 | $(-1,840) | - | $28,990 | 7,950 | $9,620 | 6,370 | $25,430 | 6,370 | - | - | $31,400 951,500 kWh |
$17,870 1,315 kW-months/year |
$(-1,840) - $ |
$28,990 7,950 MMBtu |
$9,620 6,370 Tgal |
$25,430 6,370 Tgal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Usage | Water Disposal | Personnel Changes | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Usage | Water Disposal | Personnel Changes |