IAC Assessment: WI0007
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: WI0007
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Wisconsin, Milwaukee
Assessment Year 1987
Principal Product WATER SOFTENER CONTROLS
NAICS n/a
SIC 3491 - Industrial Valves
Sales $10,000,000-$50,000,000
# of Employees 125
Plant Area (Sq.Ft.) 0
Annual Production 150,000 Pieces
Production Hrs. Annual 2,125
Location (State) WI
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $64,599 945,780 kWh $0.07
Natural Gas $17,572 3,317 MMBtu $5.30
TOTAL ENERGY COSTS $82,171
RECOMMENDED SAVINGS* $3,539 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $2,905
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes
$ kWh $ MMBtu $ $
01: 2.4312 IMPROVE LUBRICATION PRACTICES Savings:
$330
Cost:
-
$330 4,982 - - - - $330
4,982
kWh
-
-
MMBtu
-
-
$
02: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$112
Cost:
-
$112 1,758 - - - - $112
1,758
kWh
-
-
MMBtu
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,549
Cost:
$5,631
$1,549 22,567 - - - - $1,549
22,567
kWh
-
-
MMBtu
-
-
$
04: 2.6121 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED Savings:
$129
Cost:
-
- - $129 24 - - -
-
kWh
$129
24
MMBtu
-
-
$
05: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$634
Cost:
-
$634 - - - - - $634
-
kWh
-
-
MMBtu
-
-
$
06: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$387
Cost:
-
- - $387 73 - - -
-
kWh
$387
73
MMBtu
-
-
$
07: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$398
Cost:
$500
- - $498 94 $(-100) - -
-
kWh
$498
94
MMBtu
$(-100)
-
$
TOTAL RECOMMENDED Savings:
$3,539
Cost:
$6,131
$2,625 29,307 $1,014 191 $(-100) - $2,625
29,307
kWh
$1,014
191
MMBtu
$(-100)
-
$
TOTAL IMPLEMENTED Savings:
$2,905
Cost:
$6,131
$1,991 29,307 $1,014 191 $(-100) - $1,991
29,307
kWh
$1,014
191
MMBtu
$(-100)
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes