Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 1999 |
Principal Product | Aluminum, Bronze, and Copper Alloys |
NAICS | n/a |
SIC | 3366 - Copper Foundries |
Sales | $10,000,000-$50,000,000 |
# of Employees | 254 |
Plant Area (Sq.Ft.) | 550,190 |
Annual Production | 14,000,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $363,578 | 13,952,228 | kWh | $0.03 |
Electricity Demand | $392,651 | 43,108 | kW-months/year | $9.11 |
Electricity Fees | $73,590 | - | $ | - |
Natural Gas | $416,938 | 114,854 | MMBtu | $3.63 |
TOTAL ENERGY COSTS | $1,280,940 | |||
RECOMMENDED SAVINGS* | $75,539 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $13,478 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $26,146 Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | $26,146 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
$26,146 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1221 REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES |
Savings: $21,494 Cost: $72,000 |
- | - | - | - | $21,494 | 5,921 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$21,494 5,921 MMBtu |
- - Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.3131 USE EVAPORATION TO CONCENTRATE MATERIAL |
Savings: $13,199 Cost: $16,000 |
- | - | - | - | $(-1,189) | (-328) | - | - | $17,388 | 33,120 | $(-3,000) | - | - | - |
- - kWh |
- - kW-months/year |
$(-1,189) (-328) MMBtu |
- - Tgal |
$17,388 33,120 gal |
$(-3,000) - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4114 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER |
Savings: $6,159 Cost: $22,000 |
$(-575) | (-20,809) | $(-403) | (-42) | - | - | $7,137 | 10,404,990 | - | - | - | - | - | - |
$(-575) (-20,809) kWh |
$(-403) (-42) kW-months/year |
- - MMBtu |
$7,137 10,404,990 Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $4,879 Cost: - |
- | - | $4,879 | 504 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
$4,879 504 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,440 Cost: $640 |
$1,630 | 59,203 | $810 | 84 | - | - | - | - | - | - | - | - | - | - |
$1,630 59,203 kWh |
$810 84 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $785 Cost: $624 |
$462 | 16,706 | $323 | 34 | - | - | - | - | - | - | - | - | - | - |
$462 16,706 kWh |
$323 34 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $437 Cost: $243 |
$289 | 10,551 | $148 | 15 | - | - | - | - | - | - | - | - | - | - |
$289 10,551 kWh |
$148 15 kW-months/year |
- - MMBtu |
- - Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $75,539 Cost: $111,507 |
$1,806 | 65,651 | $5,757 | 595 | $20,305 | 5,593 | $7,137 | 10,404,990 | $17,388 | 33,120 | $(-3,000) | - | $26,146 | - | $1,806 65,651 kWh |
$5,757 595 kW-months/year |
$20,305 5,593 MMBtu |
$7,137 10,404,990 Tgal |
$17,388 33,120 gal |
$(-3,000) - $ |
$26,146 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $13,478 Cost: $22,640 |
$1,055 | 38,394 | $5,286 | 546 | - | - | $7,137 | 10,404,990 | - | - | - | - | - | - | $1,055 38,394 kWh |
$5,286 546 kW-months/year |
- - MMBtu |
$7,137 10,404,990 Tgal |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | gal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Other Liquid (haz) | Personnel Changes | Administrative Changes |