Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 2000 |
Principal Product | Publication Insert Services |
NAICS | n/a |
SIC | 2752 - Commercial Printing, Lithographic |
Sales | $10,000,000-$50,000,000 |
# of Employees | 450 |
Plant Area (Sq.Ft.) | 310,000 |
Annual Production | 1,000,000,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | IL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $131,834 | 3,713,951 | kWh | $0.04 |
Electricity Demand | $92,312 | 7,578 | kW-months/year | $12.18 |
Electricity Fees | $12,401 | - | $ | - |
Natural Gas | $50,290 | 13,517 | MMBtu | $3.72 |
TOTAL ENERGY COSTS | $225,868 | |||
RECOMMENDED SAVINGS* | $1,000,889 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $907,855 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS |
Savings: $416,000 Cost: $140,000 |
- | - | - | - | - | - | - | - | - | - | $416,000 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$416,000 - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.512 CONDENSE OPERATION INTO ONE BUILDING |
Savings: $280,000 Cost: $60,000 |
- | - | - | - | - | - | - | - | - | - | - | - | $280,000 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
$280,000 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.452 ELIMINATE SHIFT |
Savings: $208,000 Cost: - |
- | - | - | - | - | - | - | - | - | - | $208,000 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$208,000 - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.623 EMPLOY MODULAR JIGS TO REDUCE PROCESS SET-UP TIME |
Savings: $62,609 Cost: $2,520 |
- | - | - | - | - | - | - | - | - | - | $62,400 | - | - | - | - | - | $209 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
$62,400 - $ |
- - $ |
- - $ |
$209 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $16,591 Cost: $22,283 |
$10,850 | 291,032 | $5,741 | 449 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$10,850 291,032 kWh |
$5,741 449 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $6,364 Cost: $675 |
$4,059 | 108,734 | $2,305 | 180 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$4,059 108,734 kWh |
$2,305 180 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.8142 DISTILL CONTAMINATED SOLVENTS FOR REUSE |
Savings: $4,097 Cost: $7,825 |
- | - | - | - | - | - | $5,382 | 463 | $(-302) | (-276) | $(-682) | - | - | - | $(-301) | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$5,382 463 gal |
$(-302) (-276) lb |
$(-682) - $ |
- - $ |
$(-301) - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $3,855 Cost: $500 |
- | - | - | - | $3,855 | 1,036 | - | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$3,855 1,036 MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2515 USE OPTIMUM THICKNESS INSULATION |
Savings: $1,052 Cost: $1,084 |
- | - | - | - | $1,052 | 283 | - | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,052 283 MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $969 Cost: $740 |
$570 | 15,240 | $399 | 31 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$570 15,240 kWh |
$399 31 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $957 Cost: $300 |
- | - | $957 | 63 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
$957 63 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $395 Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | $395 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
$395 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $1,000,889 Cost: $235,927 |
$15,479 | 415,006 | $9,402 | 723 | $4,907 | 1,319 | $5,382 | 463 | $(-302) | (-276) | $685,718 | - | $280,395 | - | $(-301) | - | $209 | - | $15,479 415,006 kWh |
$9,402 723 kW-months/year |
$4,907 1,319 MMBtu |
$5,382 463 gal |
$(-302) (-276) lb |
$685,718 - $ |
$280,395 - $ |
$(-301) - $ |
$209 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $907,855 Cost: $200,500 |
- | - | - | - | $3,855 | 1,036 | - | - | - | - | $624,000 | - | $280,000 | - | - | - | - | - | - - kWh |
- - kW-months/year |
$3,855 1,036 MMBtu |
- - gal |
- - lb |
$624,000 - $ |
$280,000 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | Ancillary Material Cost |