Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 2001 |
Principal Product | Frozen Bakery |
NAICS | n/a |
SIC | 2051 - Bread, Cake, And Related Products |
Sales | $50,000,000-$100,000,000 |
# of Employees | 389 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 75,000,000 Pounds |
Production Hrs. Annual | 6,150 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $487,301 | 18,780,768 | kWh | $0.03 |
Electricity Demand | $340,377 | 37,701 | kW-months/year | $9.03 |
Electricity Fees | $48,581 | - | $ | - |
Natural Gas | $212,344 | 40,468 | MMBtu | $5.25 |
TOTAL ENERGY COSTS | $1,168,614 | |||
RECOMMENDED SAVINGS* | $376,991 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT |
Savings: $129,888 Cost: $20,000 |
- | - | - | - | - | - | $129,888 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$129,888 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE |
Savings: $120,634 Cost: $360,000 |
$80,536 | 2,960,874 | $40,098 | 4,230 | - | - | - | - |
$80,536 2,960,874 kWh |
$40,098 4,230 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $116,146 Cost: $630,000 |
$89,910 | 2,700,000 | $102,384 | 10,800 | $(-69,848) | (-13,304) | $(-6,300) | - |
$89,910 2,700,000 kWh |
$102,384 10,800 kW-months/year |
$(-69,848) (-13,304) MMBtu |
$(-6,300) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $8,467 Cost: $18,150 |
- | - | $8,467 | 617 | - | - | - | - |
- - kWh |
$8,467 617 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $1,260 Cost: $500 |
- | - | - | - | $1,260 | 240 | - | - |
- - kWh |
- - kW-months/year |
$1,260 240 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $596 Cost: - |
$395 | 14,514 | $201 | 21 | - | - | - | - |
$395 14,514 kWh |
$201 21 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $376,991 Cost: $1,028,650 |
$170,841 | 5,675,388 | $151,150 | 15,668 | $(-68,588) | (-13,064) | $123,588 | - | $170,841 5,675,388 kWh |
$151,150 15,668 kW-months/year |
$(-68,588) (-13,064) MMBtu |
$123,588 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes |