Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Wisconsin, Milwaukee |
---|---|
Assessment Year | 2006 |
Principal Product | Printed and laminated cardboard products |
NAICS | 332215 - Metal Kitchen Cookware, Utensil, Cutlery, and Flatware (except Precious) Manufacturing |
SIC | 2653 - Corrugated And Solid Fiber Boxes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 60 |
Plant Area (Sq.Ft.) | 115,000 |
Annual Production | 16,800,000 Pounds |
Production Hrs. Annual | 4,000 |
Location (State) | WI |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $44,464 | 1,144,943 | kWh | $0.04 |
Electricity Demand | $29,143 | 3,701 | kW-months/year | $7.87 |
Natural Gas | $34,588 | 3,805 | MMBtu | $9.09 |
TOTAL ENERGY COSTS | $108,195 | |||
RECOMMENDED SAVINGS* | $28,456 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $17,566 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.447 AUTOMATE PAYROLL SYSTEM |
Savings: $10,890 Cost: $6,000 |
- | - | - | - | - | - | $10,890 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$10,890 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $8,256 Cost: $850 |
- | - | - | - | $8,256 | 908 | - | - |
- - kWh |
- - kW-months/year |
$8,256 908 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,167 Cost: $8,820 |
$1,969 | 48,020 | $1,198 | 144 | - | - | - | - |
$1,969 48,020 kWh |
$1,198 144 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $2,712 Cost: - |
- | - | $2,712 | 298 | - | - | - | - |
- - kWh |
$2,712 298 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $2,149 Cost: - |
$685 | 16,710 | $1,464 | 161 | - | - | - | - |
$685 16,710 kWh |
$1,464 161 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $446 Cost: - |
$268 | 6,538 | $178 | 20 | - | - | - | - |
$268 6,538 kWh |
$178 20 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $290 Cost: $640 |
$165 | 4,019 | $125 | 15 | - | - | - | - |
$165 4,019 kWh |
$125 15 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $283 Cost: $150 |
$283 | 6,912 | - | - | - | - | - | - |
$283 6,912 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $263 Cost: - |
$217 | 5,305 | $46 | 20 | - | - | - | - |
$217 5,305 kWh |
$46 20 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $28,456 Cost: $16,460 |
$3,587 | 87,504 | $5,723 | 658 | $8,256 | 908 | $10,890 | - | $3,587 87,504 kWh |
$5,723 658 kW-months/year |
$8,256 908 MMBtu |
$10,890 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $17,566 Cost: $10,460 |
$3,587 | 87,504 | $5,723 | 658 | $8,256 | 908 | - | - | $3,587 87,504 kWh |
$5,723 658 kW-months/year |
$8,256 908 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |