Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 1993 |
Principal Product | Decorated Glass |
NAICS | n/a |
SIC | 3231 - Products Of Purchased Glass |
Sales | $5,000,000-$10,000,000 |
# of Employees | 135 |
Plant Area (Sq.Ft.) | 110,000 |
Annual Production | 0 Units |
Production Hrs. Annual | 2,080 |
Location (State) | WV |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $154,183 | 2,150,938 | kWh | $0.07 |
Natural Gas | $171,828 | 50,153 | MMBtu | $3.43 |
TOTAL ENERGY COSTS | $326,011 | |||
RECOMMENDED SAVINGS* | $36,107 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $36,107 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $320 Cost: $244 |
- | - | $320 | 93 |
- - kWh |
$320 93 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $375 Cost: $180 |
$375 | 13,775 | - | - |
$375 13,775 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $2,363 Cost: $2,400 |
- | - | $2,363 | 701 |
- - kWh |
$2,363 701 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2428 USE FLUE GASES IN RADIANT HEATER FOR SPACE HEATING, OVENS, ETC |
Savings: $2,285 Cost: $1,392 |
- | - | $2,285 | 666 |
- - kWh |
$2,285 666 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $2,233 Cost: $1,371 |
- | - | $2,233 | 651 |
- - kWh |
$2,233 651 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $29 Cost: $23 |
- | - | $29 | 9 |
- - kWh |
$29 9 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,327 Cost: $850 |
- | - | $1,327 | 387 |
- - kWh |
$1,327 387 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $332 Cost: $1,450 |
$332 | 12,309 | - | - |
$332 12,309 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $160 Cost: $6,080 |
$160 | 5,862 | - | - |
$160 5,862 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.1192 REDUCE SCRAP PRODUCTION |
Savings: $26,683 Cost: - |
$26,683 | - | - | - |
$26,683 - kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $36,107 Cost: $13,990 |
$27,550 | 31,946 | $8,557 | 2,507 | $27,550 31,946 kWh |
$8,557 2,507 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $36,107 Cost: $13,990 |
$27,550 | 31,946 | $8,557 | 2,507 | $27,550 31,946 kWh |
$8,557 2,507 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |