Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | West Virginia University |
---|---|
Assessment Year | 2022 |
Principal Product | Sauna |
NAICS | 326191 - Plastics Plumbing Fixture Manufacturing |
SIC | 3088 - Plastics Plumbing Fixtures |
Sales | $10,000,000-$50,000,000 |
# of Employees | 50 |
Plant Area (Sq.Ft.) | 96,000 |
Annual Production | 8,000 Units |
Production Hrs. Annual | 2,080 |
Location (State) | WV |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $36,088 | 765,280 | kWh | $0.05 |
Electricity Demand | $50,938 | 3,083 | kW-months/year | $16.52 |
Electricity Fees | $2,388 | - | $ | - |
Natural Gas | $7,358 | 757 | MMBtu | $9.72 |
Other Energy | $12,134 | 268 | MMBtu | $45.28 |
TOTAL ENERGY COSTS | $108,906 | |||
RECOMMENDED SAVINGS* | $36,278 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $15,606 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $13,183 Cost: $4,755 |
- | - | $13,183 | 798 | - | - | - | - |
- - kWh |
$13,183 798 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $9,625 Cost: $18,739 |
$4,091 | 86,677 | $5,534 | 335 | - | - | - | - |
$4,091 86,677 kWh |
$5,534 335 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6242 MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION |
Savings: $4,546 Cost: $5,490 |
$1,506 | 31,909 | $3,040 | 184 | - | - | - | - |
$1,506 31,909 kWh |
$3,040 184 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,868 Cost: $465 |
$952 | 20,172 | $1,916 | 116 | - | - | - | - |
$952 20,172 kWh |
$1,916 116 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $1,927 Cost: $2,021 |
$698 | 14,793 | $1,229 | 74 | - | - | - | - |
$698 14,793 kWh |
$1,229 74 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $670 Cost: $78 |
$224 | 4,743 | $446 | 27 | - | - | - | - |
$224 4,743 kWh |
$446 27 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $299 Cost: $465 |
$101 | 2,141 | $198 | 12 | - | - | - | - |
$101 2,141 kWh |
$198 12 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $217 Cost: $598 |
$94 | 1,992 | $182 | 11 | - | - | $(-59) | - |
$94 1,992 kWh |
$182 11 kW-months/year |
- - MMBtu |
$(-59) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $2,943 Cost: $7,374 |
$(-31) | (-661) | - | - | $2,974 | 306 | - | - |
$(-31) (-661) kWh |
- - kW-months/year |
$2,974 306 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $36,278 Cost: $39,985 |
$7,635 | 161,766 | $25,728 | 1,557 | $2,974 | 306 | $(-59) | - | $7,635 161,766 kWh |
$25,728 1,557 kW-months/year |
$2,974 306 MMBtu |
$(-59) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $15,606 Cost: $22,366 |
$6,160 | 130,518 | $9,505 | 575 | - | - | $(-59) | - | $6,160 130,518 kWh |
$9,505 575 kW-months/year |
- - MMBtu |
$(-59) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost |