Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,033
matching recommendationsNAICS | 221 | Utilities |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MZ0344 # 02 Y:2023 | 02 | 2023 | INSTALL OCCUPANCY SENSORS | $1,547 | $1,000 | Implemented |
MZ0344 # 01 Y:2023 | 01 | 2023 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,614 | $750 | Implemented |
MZ0344 # 04 Y:2023 | 04 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $59,175 | $0 | Implemented |
SF0602 # 06 Y:2023 | 06 | 2023 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $6,247 | $30,019 | Implemented |
OK1090 # 03 Y:2023 | 03 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,602 | $1,797 | Implemented |
OK1090 # 02 Y:2023 | 02 | 2023 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $172 | $530 | Implemented |
OK1090 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,316 | $3,638 | Implemented |
OK1090 # 01 Y:2023 | 01 | 2023 | USE COUNTER CURRENT RINSING TO REDUCE WASTE WATER | $76,727 | $51,456 | Implemented |
MUWT01 # 05 Y:2023 | 05 | 2023 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $120 | $0 | Implemented |
MUWT01 # 04 Y:2023 | 04 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $715 | $0 | Implemented |
SF0599 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $49,633 | $13,122 | Implemented |
SF0599 # 01 Y:2023 | 01 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $8,702 | $0 | Implemented |
SF0599 # 04 Y:2023 | 04 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,031 | $15,452 | Implemented |
TR0039 # 03 Y:2022 | 03 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $68,177 | $780,672 | Implemented |
TR0039 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $512 | $375 | Implemented |
TR0038 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $337 | $921 | Implemented |
TR0038 # 04 Y:2022 | 04 | 2022 | MAINTAIN MACHINES TO REDUCE LEAKS | $717 | $884 | Implemented |
TR0038 # 02 Y:2022 | 02 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $303 | $583 | Implemented |
MA0852 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $99,365 | $854,943 | Implemented |
MA0852 # 08 Y:2023 | 08 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,591 | $1,544 | Implemented |
LT8367 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $209 | $343 | Implemented |
LT8367 # 02 Y:2023 | 02 | 2023 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $2,629 | $335,972 | Implemented |
LT8367 # 03 Y:2023 | 03 | 2023 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $7,506 | $3,722 | Implemented |
AS0543 # 02 Y:2023 | 02 | 2023 | AIR CONDITION ONLY SPACE NECESSARY | $1,804 | $8,019 | Implemented |
AS0543 # 05 Y:2023 | 05 | 2023 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $150 | $92 | Implemented |