IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

188

matching recommendations
Reset
NAICS 221 Utilities
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UF0607 # 01 Y:2023 01 2023 USE DEMAND CONTROLLER OR LOAD SHEDDER $173,293 $118,890 n/a
UF0607 # 03 Y:2023 03 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $94,496 $322,608 n/a
UF0607 # 05 Y:2023 05 2023 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $3,683 $0 n/a
UF0607 # 04 Y:2023 04 2023 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $36,207 $25,350 n/a
UF0607 # 06 Y:2023 06 2023 LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT $183,418 $60,000 n/a
UF0607 # 02 Y:2023 02 2023 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $122,669 $11,700 n/a
UF0606 # 02 Y:2023 02 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $65,322 $322,608 n/a
UF0606 # 04 Y:2023 04 2023 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $35,430 $25,350 n/a
UF0606 # 05 Y:2023 05 2023 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $5,283 $0 n/a
UF0606 # 03 Y:2023 03 2023 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $38,799 $79,800 n/a
UF0606 # 06 Y:2023 06 2023 LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT $214,485 $60,000 n/a
UF0606 # 01 Y:2023 01 2023 USE DEMAND CONTROLLER OR LOAD SHEDDER $188,564 $146,067 n/a
UF0604 # 08 Y:2023 08 2023 LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS $10,959 $0 Implemented
UF0604 # 01 Y:2023 01 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $48,311 $293,280 Not Implemented
UF0604 # 04 Y:2023 04 2023 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS $3,173 $0 Implemented
UF0604 # 06 Y:2023 06 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,334 $6,383 Not Implemented
UF0604 # 03 Y:2023 03 2023 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $8,590 $37,275 Implemented
UF0604 # 07 Y:2023 07 2023 LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT $63,559 $10,000 Implemented
UF0604 # 02 Y:2023 02 2023 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $30,577 $37,582 Implemented
UF0604 # 05 Y:2023 05 2023 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS $2,430 $780 Implemented
UF0581 # 05 Y:2022 05 2022 LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT $11,526 $10,000 Implemented
UF0581 # 07 Y:2022 07 2022 LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS $2,191 $0 Implemented
UF0581 # 01 Y:2022 01 2022 USE SOLAR HEAT TO MAKE ELECTRICTY $74,168 $293,280 Not Implemented
UF0581 # 04 Y:2022 04 2022 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $5,091 $8,250 Implemented
UF0581 # 02 Y:2022 02 2022 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $17,084 $4,202 Implemented