Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,275
matching recommendationsNAICS | 221 | Utilities |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0494 # 08 Y:2020 | 08 | 2020 | INSTALL HEAT PIPES / RAISE COOLING SETPOINT | $61 | $47 | Implemented |
AS0492 # 01 Y:2020 | 01 | 2020 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $16,087 | $3,941 | Implemented |
AS0492 # 02 Y:2020 | 02 | 2020 | TURN OFF EQUIPMENT WHEN NOT IN USE | $6,291 | $789 | Implemented |
AS0492 # 03 Y:2020 | 03 | 2020 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,170 | $4,695 | Not Implemented |
AS0492 # 04 Y:2020 | 04 | 2020 | USE SYNTHETIC LUBRICANT | $1,708 | $300 | Not Implemented |
AS0492 # 05 Y:2020 | 05 | 2020 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $1,465 | $244 | Not Implemented |
AS0492 # 06 Y:2020 | 06 | 2020 | KEEP EQUIPMENT CLEAN | $743 | $464 | Not Implemented |
AS0492 # 07 Y:2020 | 07 | 2020 | INSTALL OCCUPANCY SENSORS | $220 | $612 | Not Implemented |
IC0243 # 01 Y:2020 | 01 | 2020 | USE EXISTING DAM TO GENERATE ELECTRICITY | $1,582 | $31,846 | Not Implemented |
IC0243 # 02 Y:2020 | 02 | 2020 | USE SOLAR HEAT TO MAKE ELECTRICTY | $37,674 | $140,751 | Implemented |
IC0243 # 03 Y:2020 | 03 | 2020 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $21,698 | $6,150 | Implemented |
IC0243 # 04 Y:2020 | 04 | 2020 | USE OPTIMUM TEMPERATURE | $24,347 | $0 | Not Implemented |
IC0243 # 05 Y:2020 | 05 | 2020 | SEPARATE TREATMENTS FOR EACH TYPE OF SOLUTION AND RECYCLE | $21,681 | $40,000 | Not Implemented |
IC0243 # 06 Y:2020 | 06 | 2020 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $130,722 | $713,750 | Implemented |
UU0174 # 01 Y:2021 | 01 | 2021 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $24,060 | $178,852 | Implemented |
UU0174 # 02 Y:2021 | 02 | 2021 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $18,383 | $85,347 | Implemented |
UU0174 # 03 Y:2021 | 03 | 2021 | INSTALL OCCUPANCY SENSORS | $5,107 | $43,420 | Not Implemented |
UU0174 # 04 Y:2021 | 04 | 2021 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $744 | $200 | Implemented |
UU0174 # 05 Y:2021 | 05 | 2021 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $476 | $1,925 | Not Implemented |
OK1038 # 01 Y:2021 | 01 | 2021 | INSTALL OCCUPANCY SENSORS | $563 | $1,944 | Not Implemented |
OK1038 # 02 Y:2021 | 02 | 2021 | USE COUNTER CURRENT RINSING TO REDUCE WASTE WATER | $24,443 | $2,171 | Not Implemented |
OK1038 # 03 Y:2021 | 03 | 2021 | INSTALL TIMERS AND/OR THERMOSTATS | $991 | $0 | Not Implemented |
OR0740 # 01 Y:2021 | 01 | 2021 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $69,219 | $8,189 | Implemented |
OR0740 # 02 Y:2021 | 02 | 2021 | UPGRADE OBSOLETE EQUIPMENT | $68,316 | $149,022 | Not Implemented |
OR0740 # 03 Y:2021 | 03 | 2021 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $54,988 | $79,709 | Implemented |