Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,132
matching recommendationsNAICS | 311 | Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0257 # 02 Y:2004 | 02 | 2004 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $67,341 | $2,000 | Implemented |
MS0257 # 03 Y:2004 | 03 | 2004 | REPAIR AND ELIMINATE STEAM LEAKS | $36,924 | $54 | Implemented |
MS0257 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $15,325 | $348 | Implemented |
MS0257 # 06 Y:2004 | 06 | 2004 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $6,318 | $2,673 | Implemented |
MS0257 # 10 Y:2004 | 10 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $632 | $1,029 | Implemented |
UU0067 # 01 Y:2004 | 01 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $25,126 | $0 | Implemented |
UU0067 # 04 Y:2004 | 04 | 2004 | INSTALL WIND POWERED ELECTRIC GENERATOR | $0 | $0 | Implemented |
WV0301 # 01 Y:2004 | 01 | 2004 | INSULATE BARE EQUIPMENT | $30,817 | $4,062 | Implemented |
WV0301 # 02 Y:2004 | 02 | 2004 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $15,918 | $4,120 | Implemented |
WV0301 # 03 Y:2004 | 03 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,529 | $14,877 | Implemented |
WV0301 # 04 Y:2004 | 04 | 2004 | DEVELOP A REPAIR/REPLACE POLICY | $6,476 | $360 | Implemented |
WV0301 # 05 Y:2004 | 05 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,088 | $1,890 | Implemented |
WV0301 # 07 Y:2004 | 07 | 2004 | REPAIR OR REPLACE STEAM TRAPS | $3,558 | $1,000 | Implemented |
WV0301 # 08 Y:2004 | 08 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,925 | $120 | Implemented |
WV0301 # 10 Y:2004 | 10 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,362 | $175 | Implemented |
WV0301 # 11 Y:2004 | 11 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,293 | $0 | Implemented |
LL0199 # 01 Y:2004 | 01 | 2004 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $33,535 | $960 | Implemented |
LL0199 # 02 Y:2004 | 02 | 2004 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $25,020 | $2,910 | Implemented |
LL0199 # 03 Y:2004 | 03 | 2004 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $13,735 | $304 | Implemented |
LL0199 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,985 | $720 | Implemented |
LL0199 # 06 Y:2004 | 06 | 2004 | USE PHOTOCELL CONTROLS | $935 | $525 | Implemented |
LL0199 # 07 Y:2004 | 07 | 2004 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $544 | $585 | Implemented |
LL0199 # 08 Y:2004 | 08 | 2004 | INSTALL OCCUPANCY SENSORS | $292 | $120 | Implemented |
LL0199 # 09 Y:2004 | 09 | 2004 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $41,244 | $0 | Implemented |
LL0199 # 10 Y:2004 | 10 | 2004 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $4,740 | $5,697 | Implemented |