Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,562
matching recommendationsNAICS | 311 | Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0272 # 12 Y:2003 | 12 | 2003 | USE SYNTHETIC LUBRICANT | $1,058 | $240 | Implemented |
WV0272 # 13 Y:2003 | 13 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,205 | $80 | Implemented |
SD0328 # 01 Y:2003 | 01 | 2003 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $269,910 | $1,371,000 | Implemented |
SD0328 # 02 Y:2003 | 02 | 2003 | INSTALL SKYLIGHTS | $5,260 | $6,650 | Not Implemented |
SD0328 # 03 Y:2003 | 03 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,323 | $0 | Implemented |
SD0328 # 04 Y:2003 | 04 | 2003 | INSTALL OCCUPANCY SENSORS | $747 | $400 | Not Implemented |
SD0328 # 05 Y:2003 | 05 | 2003 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $12,600 | $11,000 | Not Implemented |
SD0328 # 06 Y:2003 | 06 | 2003 | REDUCE SCRAP PRODUCTION | $4,246 | $342 | Not Implemented |
SD0328 # 07 Y:2003 | 07 | 2003 | INSTALL AUTOMATIC PACKING EQUIPMENT | $401,960 | $800,000 | Not Implemented |
SD0328 # 08 Y:2003 | 08 | 2003 | REDESIGN PROCESS | $55,557 | $24,000 | Not Implemented |
SU0164 # 01 Y:2003 | 01 | 2003 | INSTALL WIND POWERED ELECTRIC GENERATOR | $141,258 | $1,171,875 | Not Implemented |
SU0164 # 02 Y:2003 | 02 | 2003 | USE OPTIMUM THICKNESS INSULATION | $115,419 | $348,540 | Implemented |
SU0164 # 03 Y:2003 | 03 | 2003 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $30,000 | $76,518 | Not Implemented |
SU0164 # 04 Y:2003 | 04 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,096 | $55,580 | Implemented |
SU0164 # 05 Y:2003 | 05 | 2003 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $8,721 | $0 | Implemented |
SU0164 # 06 Y:2003 | 06 | 2003 | INSTALL WIND POWERED ELECTRIC GENERATOR | $7,910 | $10,000 | Not Implemented |
SU0164 # 07 Y:2003 | 07 | 2003 | REDESIGN PROCESS | $6,861 | $270 | Implemented |
SU0164 # 08 Y:2003 | 08 | 2003 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,485 | $700 | Implemented |
SU0164 # 09 Y:2003 | 09 | 2003 | INCREASE AMOUNT OF CONDENSATE RETURNED | $1,293 | $955 | Implemented |
SU0164 # 10 Y:2003 | 10 | 2003 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $847 | $1,744 | Implemented |
SU0164 # 11 Y:2003 | 11 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $723 | $608 | Implemented |
SU0164 # 12 Y:2003 | 12 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $550 | $0 | Implemented |
SU0164 # 13 Y:2003 | 13 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $462 | $29 | Implemented |
SU0164 # 14 Y:2003 | 14 | 2003 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $198 | $150 | Not Implemented |
SF0265 # 01 Y:2003 | 01 | 2003 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $9,390 | $380 | Not Implemented |