Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
9,562
matching recommendationsNAICS | 311 | Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0260 # 13 Y:2003 | 13 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $298 | $40 | Implemented |
WV0260 # 14 Y:2003 | 14 | 2003 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $26,307 | $1,855 | Not Implemented |
SD0316 # 01 Y:2003 | 01 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,055 | $3,750 | Not Implemented |
SD0316 # 02 Y:2003 | 02 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,922 | $0 | Implemented |
SD0316 # 03 Y:2003 | 03 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,991 | $300 | Implemented |
SD0316 # 04 Y:2003 | 04 | 2003 | INSTALL SKYLIGHTS | $872 | $1,000 | Not Implemented |
SD0316 # 05 Y:2003 | 05 | 2003 | UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS | $47,600 | $40,000 | Not Implemented |
SD0316 # 06 Y:2003 | 06 | 2003 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $11,188 | $10,000 | Not Implemented |
SD0316 # 07 Y:2003 | 07 | 2003 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $2,955 | $9,800 | Not Implemented |
GT0751 # 01 Y:2003 | 01 | 2003 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $5,286 | $450 | Not Implemented |
GT0751 # 02 Y:2003 | 02 | 2003 | ADJUST BURNERS FOR EFFICIENT OPERATION | $31,370 | $5,000 | Implemented |
GT0751 # 03 Y:2003 | 03 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $7,017 | $0 | Implemented |
GT0751 # 04 Y:2003 | 04 | 2003 | INSTALL OCCUPANCY SENSORS | $697 | $50 | Implemented |
GT0751 # 05 Y:2003 | 05 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $54,294 | $54,294 | n/a |
GT0751 # 06 Y:2003 | 06 | 2003 | IMPROVE COMBUSTION CONTROL CAPABILITY | $133,000 | $622,000 | Not Implemented |
GT0751 # 07 Y:2003 | 07 | 2003 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $4,433 | $111 | Not Implemented |
GT0751 # 08 Y:2003 | 08 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,580 | $12,000 | Implemented |
GT0751 # 09 Y:2003 | 09 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,221 | $11,587 | Implemented |
GT0751 # 10 Y:2003 | 10 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $11,690 | $72,250 | Implemented |
LM0051 # 01 Y:2003 | 01 | 2003 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,243 | $1,760 | Implemented |
LM0051 # 02 Y:2003 | 02 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,478 | $1,466 | Implemented |
LM0051 # 03 Y:2003 | 03 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $510 | $210 | Implemented |
LM0051 # 04 Y:2003 | 04 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $192 | $150 | Implemented |
LM0051 # 05 Y:2003 | 05 | 2003 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $7,233 | $3,600 | Implemented |
LM0051 # 06 Y:2003 | 06 | 2003 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $145,000 | $38,029 | Implemented |