IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

251

matching recommendations
Reset
NAICS 311 Food Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
DL0063 # 15 Y:2010 15 2010 CLOSE OFF UNNEEDED STEAM LINES $3,627 $400 Implemented
DL0063 # 16 Y:2010 16 2010 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $3,700 $2,100 Not Implemented
DL0063 # 17 Y:2010 17 2010 INSULATE BARE EQUIPMENT $3,993 $30,400 Not Implemented
DL0063 # 18 Y:2010 18 2010 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $733 $615 Implemented
LE0300 # 01 Y:2010 01 2010 USE SOLAR HEAT TO MAKE ELECTRICTY $161,306 $1,080,000 Not Implemented
LE0300 # 02 Y:2010 02 2010 UPGRADE OBSOLETE EQUIPMENT $30,883 $29,000 Not Implemented
LE0300 # 03 Y:2010 03 2010 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $17,838 $19,900 Implemented
LE0300 # 04 Y:2010 04 2010 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $11,921 $2,440 Implemented
LE0300 # 05 Y:2010 05 2010 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $7,417 $30,000 Implemented
LE0300 # 06 Y:2010 06 2010 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $3,315 $3,000 Implemented
LE0300 # 07 Y:2010 07 2010 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $2,827 $1,000 Implemented
LE0300 # 08 Y:2010 08 2010 INSTALL OCCUPANCY SENSORS $8,078 $900 Implemented
LE0300 # 09 Y:2010 09 2010 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $32,263 $42,718 Implemented
LE0253 # 01 Y:2007 01 2007 INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE $41,910 $32,000 Implemented
LE0253 # 02 Y:2007 02 2007 ELIMINATE/REDUCE AN OPERATION $40,620 $4,000 Not Implemented
LE0253 # 03 Y:2007 03 2007 TURN OFF EQUIPMENT WHEN NOT IN USE $22,542 $300 Implemented
LE0253 # 04 Y:2007 04 2007 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $20,904 $300 Implemented
LE0253 # 05 Y:2007 05 2007 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $20,819 $37,000 Implemented
LE0253 # 06 Y:2007 06 2007 REPLACE HEAT TREATING OVEN WITH MORE EFFICIENT UNIT $12,436 $15,000 Not Implemented
LE0253 # 07 Y:2007 07 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $12,186 $1,000 Implemented
LE0253 # 08 Y:2007 08 2007 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,349 $6,200 Implemented
LE0253 # 09 Y:2007 09 2007 INSTALL TIMERS AND/OR THERMOSTATS $8,342 $480 Not Implemented
LE0253 # 10 Y:2007 10 2007 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $5,672 $2,500 Not Implemented
LE0253 # 11 Y:2007 11 2007 TURN OFF EQUIPMENT WHEN NOT IN USE $1,980 $510 Not Implemented
LE0253 # 12 Y:2007 12 2007 REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED $60,000 $100,000 Not Implemented