Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

331

matching recommendations
Reset
NAICS 311 Food Manufacturing
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0799 # 05 Y:2024 05 2024 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $3,006 $11,189 n/a
OR0799 # 03 Y:2024 03 2024 RECOVER WASTE HEAT FROM EQUIPMENT $32,971 $41,770 n/a
OR0799 # 04 Y:2024 04 2024 USE SOLAR HEAT TO MAKE ELECTRICTY $112,659 $399,900 n/a
OR0799 # 01 Y:2024 01 2024 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $2,039 $0 n/a
OR0799 # 02 Y:2024 02 2024 RECOVER WASTE HEAT FROM EQUIPMENT $10,927 $3,514 n/a
OR0792 # 06 Y:2024 06 2024 INSTALL OCCUPANCY SENSORS $2,667 $3,106 n/a
OR0792 # 05 Y:2024 05 2024 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION $7,380 $6,624 n/a
OR0792 # 02 Y:2024 02 2024 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $15,081 $1,119 n/a
OR0792 # 04 Y:2024 04 2024 INSTALL / REPAIR INSULATION ON STEAM LINES $6,357 $3,090 n/a
OR0792 # 03 Y:2024 03 2024 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS $37,200 $18,409 n/a
OR0792 # 01 Y:2024 01 2024 TURN OFF EQUIPMENT WHEN NOT IN USE $1,993 $0 n/a
OR0792 # 07 Y:2024 07 2024 PURCHASE EQUIPMENT INSTEAD OF LEASING $395,376 $1,242,029 n/a
OR0782 # 03 Y:2023 03 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $4,302 $41,745 Implemented
OR0782 # 01 Y:2023 01 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $3,455 $3,143 Implemented
OR0782 # 02 Y:2023 02 2023 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $34,701 $316,866 Not Implemented
OR0780 # 04 Y:2023 04 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $1,666 $24,285 Not Implemented
OR0780 # 01 Y:2023 01 2023 USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS $35,316 $540,000 Not Implemented
OR0780 # 03 Y:2023 03 2023 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS $2,453 $14,157 Not Implemented
OR0780 # 02 Y:2023 02 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $13,517 $2,000 Implemented
OR0775 # 02 Y:2023 02 2023 INSTALL OCCUPANCY SENSORS $563 $261 Not Implemented
OR0775 # 03 Y:2023 03 2023 USE SOLAR HEAT TO MAKE ELECTRICTY $2,277 $41,745 Not Implemented
OR0775 # 01 Y:2023 01 2023 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $174,406 $233,000 Not Implemented
OR0773 # 04 Y:2023 04 2023 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT $1,262 $12,121 Not Implemented
OR0773 # 02 Y:2023 02 2023 INSTALL / REPAIR INSULATION ON STEAM LINES $1,051 $797 Implemented
OR0773 # 01 Y:2023 01 2023 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS $5,439 $1,278 Implemented