Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
537
matching recommendationsNAICS | 31111 | Animal Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0433 # 04 Y:2010 | 04 | 2010 | USE STEAM CONDENSATE FOR HOT WATER SUPPLY (NON-POTABLE) | $21,987 | $10,000 | Not Implemented |
UF0433 # 05 Y:2010 | 05 | 2010 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,205 | $0 | Implemented |
UF0433 # 06 Y:2010 | 06 | 2010 | DEVELOP A REPAIR/REPLACE POLICY | $621 | $0 | Implemented |
UF0433 # 07 Y:2010 | 07 | 2010 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $11,610 | $0 | Implemented |
UF0433 # 08 Y:2010 | 08 | 2010 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $7,722 | $6,350 | Not Implemented |
UF0433 # 09 Y:2010 | 09 | 2010 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $23,836 | $4,000 | Not Implemented |
UF0433 # 10 Y:2010 | 10 | 2010 | ESTABLISH A PREVENTATIVE MAINTENANCE PROGRAM | $1,885 | $816 | Implemented |
WV0384 # 01 Y:2008 | 01 | 2008 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $13,545 | $1,000 | Not Implemented |
WV0384 # 02 Y:2008 | 02 | 2008 | DEVELOP A REPAIR/REPLACE POLICY | $10,724 | $1,094 | Implemented |
WV0384 # 03 Y:2008 | 03 | 2008 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,084 | $1,070 | Not Implemented |
WV0384 # 04 Y:2008 | 04 | 2008 | INSULATE BARE EQUIPMENT | $2,032 | $577 | Not Implemented |
WV0384 # 05 Y:2008 | 05 | 2008 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,872 | $2,000 | Not Implemented |
WV0384 # 06 Y:2008 | 06 | 2008 | OPTIMIZE PLANT POWER FACTOR | $1,800 | $11,500 | Not Implemented |
WV0384 # 07 Y:2008 | 07 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,609 | $6,026 | Implemented |
WV0384 # 08 Y:2008 | 08 | 2008 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $870 | $308 | Implemented |
WV0384 # 09 Y:2008 | 09 | 2008 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $364 | $438 | Implemented |
WV0384 # 10 Y:2008 | 10 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $352 | $25 | Implemented |
OK0766 # 01 Y:2008 | 01 | 2008 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $4,948 | $775 | Implemented |
OK0766 # 02 Y:2008 | 02 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,063 | $0 | Implemented |
OK0766 # 03 Y:2008 | 03 | 2008 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $475 | $1,937 | Implemented |
OK0766 # 04 Y:2008 | 04 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,350 | $11,729 | Not Implemented |
OK0766 # 05 Y:2008 | 05 | 2008 | Install Anaerobic Digester | $304,567 | $240,000 | Not Implemented |
UD0780 # 01 Y:2008 | 01 | 2008 | INSULATE BARE EQUIPMENT | $31,350 | $8,290 | Not Implemented |
UD0780 # 02 Y:2008 | 02 | 2008 | FLASH CONDENSATE TO PRODUCE LOWER PRESSURE STEAM | $28,671 | $23,190 | Not Implemented |
UD0780 # 03 Y:2008 | 03 | 2008 | ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF | $14,100 | $18,000 | Not Implemented |