Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
305
matching recommendationsNAICS | 3112 | Grain and Oilseed Milling |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0549 # 09 Y:2016 | 09 | 2016 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $329 | $1,151 | Implemented |
IP0053 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $456 | $924 | Implemented |
IP0053 # 04 Y:2015 | 04 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $4,650 | $2,685 | Implemented |
IP0053 # 03 Y:2015 | 03 | 2015 | APPLY FOR INVESTMENT INCENTIVES | $38,029 | $5,000 | Implemented |
IP0053 # 02 Y:2015 | 02 | 2015 | INSTALL OCCUPANCY SENSORS | $1,294 | $160 | Implemented |
IP0053 # 01 Y:2015 | 01 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $57,305 | $915 | Implemented |
IA0534 # 06 Y:2015 | 06 | 2015 | INSTALL / REPAIR INSULATION ON STEAM LINES | $338 | $1,008 | Implemented |
IA0534 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $356 | $269 | Implemented |
IA0534 # 04 Y:2015 | 04 | 2015 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $590 | $2,620 | Implemented |
IA0534 # 02 Y:2015 | 02 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $5,029 | $542 | Implemented |
IA0534 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,201 | $9,836 | Implemented |
BD0448 # 15 Y:2014 | 15 | 2014 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $10,650 | $30,000 | Implemented |
BD0448 # 13 Y:2014 | 13 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $668 | $600 | Implemented |
BD0448 # 12 Y:2014 | 12 | 2014 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $1,070 | $40 | Implemented |
BD0448 # 09 Y:2014 | 09 | 2014 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,990 | $1,000 | Implemented |
BD0448 # 08 Y:2014 | 08 | 2014 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,695 | $3,000 | Implemented |
BD0448 # 07 Y:2014 | 07 | 2014 | INSTALL OCCUPANCY SENSORS | $3,869 | $1,625 | Implemented |
BD0448 # 06 Y:2014 | 06 | 2014 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $13,135 | $30,000 | Implemented |
BD0448 # 05 Y:2014 | 05 | 2014 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $13,680 | $9,880 | Implemented |
BD0448 # 04 Y:2014 | 04 | 2014 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $14,011 | $10,000 | Implemented |
BD0448 # 03 Y:2014 | 03 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,582 | $17,750 | Implemented |
BD0448 # 02 Y:2014 | 02 | 2014 | INSTALL TURBULATORS | $18,699 | $5,000 | Implemented |
BD0448 # 01 Y:2014 | 01 | 2014 | IMPROVE COMBUSTION CONTROL CAPABILITY | $51,953 | $95,000 | Implemented |
OR0629 # 04 Y:2014 | 04 | 2014 | REPLACE BOILER | $523,306 | $3,403,664 | Implemented |
OR0629 # 03 Y:2014 | 03 | 2014 | RECOVER AND REUSE COOLING WATER | $58,681 | $3,764 | Implemented |