Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
120
matching recommendationsNAICS | 3114 | Fruit and Vegetable Preserving and Specialty Food Manufacturing |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0780 # 01 Y:2023 | 01 | 2023 | USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS | $35,316 | $540,000 | Not Implemented |
OR0780 # 02 Y:2023 | 02 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,517 | $2,000 | Implemented |
OR0780 # 04 Y:2023 | 04 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $1,666 | $24,285 | Not Implemented |
OR0780 # 03 Y:2023 | 03 | 2023 | REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS | $2,453 | $14,157 | Not Implemented |
OR0775 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $2,277 | $41,745 | Not Implemented |
OR0775 # 02 Y:2023 | 02 | 2023 | INSTALL OCCUPANCY SENSORS | $563 | $261 | Not Implemented |
OR0775 # 01 Y:2023 | 01 | 2023 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $174,406 | $233,000 | Not Implemented |
OR0773 # 03 Y:2023 | 03 | 2023 | PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT | $8,507 | $13,124 | Not Implemented |
OR0773 # 04 Y:2023 | 04 | 2023 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $1,262 | $12,121 | Not Implemented |
OR0773 # 01 Y:2023 | 01 | 2023 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $5,439 | $1,278 | Implemented |
OR0773 # 02 Y:2023 | 02 | 2023 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,051 | $797 | Implemented |
OR0757 # 01 Y:2022 | 01 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,612 | $0 | Not Implemented |
OR0757 # 04 Y:2022 | 04 | 2022 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $194,400 | $300,000 | Not Implemented |
OR0757 # 02 Y:2022 | 02 | 2022 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $26,900 | $0 | Not Implemented |
OR0757 # 03 Y:2022 | 03 | 2022 | INSTALL AUTOMATIC PACKING EQUIPMENT | $97,200 | $50,000 | Not Implemented |
OR0704 # 03 Y:2018 | 03 | 2018 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $40,837 | $72,155 | Not Implemented |
OR0704 # 01 Y:2018 | 01 | 2018 | USE FILTER AND DRYING OVEN TO REDUCE SLUDGE VOLUME | $510,333 | $740,000 | Not Implemented |
OR0704 # 04 Y:2018 | 04 | 2018 | MINIMIZE WATER USAGE | $28,545 | $540 | Not Implemented |
OR0704 # 06 Y:2018 | 06 | 2018 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $5,586 | $14,266 | Not Implemented |
OR0704 # 02 Y:2018 | 02 | 2018 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $127,144 | $201,450 | Implemented |
OR0704 # 05 Y:2018 | 05 | 2018 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $12,192 | $2,161 | Not Implemented |
OR0694 # 03 Y:2017 | 03 | 2017 | INSTALL BACK-UP EQUIPMENT | $219,130 | $45,000 | Not Implemented |
OR0694 # 01 Y:2017 | 01 | 2017 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $190,250 | $7,842 | Not Implemented |
OR0694 # 02 Y:2017 | 02 | 2017 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $78,503 | $7,018 | Not Implemented |
OR0694 # 04 Y:2017 | 04 | 2017 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $29,962 | $12,100 | Not Implemented |