Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
48
matching recommendationsNAICS | 31142 | Fruit and Vegetable Canning, Pickling, and Drying |
---|
Row Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SD0389 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $264 | $1,006 | Implemented |
SD0389 # 03 Y:2006 | 03 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $433 | $2,797 | Implemented |
SD0389 # 02 Y:2006 | 02 | 2006 | USE PHOTOCELL CONTROLS | $846 | $480 | Implemented |
OR0510 # 01 Y:2006 | 01 | 2006 | CAREFULLY CONTROL WATER LEVEL IN MASS FINISHING EQUIPMENT | $61,000 | $40,000 | Implemented |
OR0510 # 03 Y:2006 | 03 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $12,200 | $35,000 | Implemented |
OR0510 # 07 Y:2006 | 07 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $4,900 | $19,200 | Implemented |
OR0508 # 06 Y:2006 | 06 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,200 | $3,200 | Implemented |
OR0508 # 02 Y:2006 | 02 | 2006 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $53,000 | $2,000 | Implemented |
OR0508 # 01 Y:2006 | 01 | 2006 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $69,500 | $30,000 | Implemented |
OR0508 # 08 Y:2006 | 08 | 2006 | UPGRADE CONTROLS ON COMPRESSORS | $5,100 | $30,000 | Implemented |
OR0508 # 07 Y:2006 | 07 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,100 | $12,000 | Implemented |
OR0508 # 03 Y:2006 | 03 | 2006 | INSTALL / REPAIR INSULATION ON STEAM LINES | $24,700 | $5,000 | Implemented |
OR0503 # 01 Y:2006 | 01 | 2006 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $37,500 | $42,500 | Implemented |
OR0503 # 03 Y:2006 | 03 | 2006 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $17,800 | $36,000 | Implemented |
OR0503 # 05 Y:2006 | 05 | 2006 | MAXIMIZE PRODUCTION RUNS TO REDUCE CLEANING | $46,500 | $0 | Implemented |
OR0503 # 04 Y:2006 | 04 | 2006 | $50,800 | $11,300 | Implemented | |
OR0503 # 06 Y:2006 | 06 | 2006 | INSTALL / REPAIR INSULATION ON STEAM LINES | $5,341 | $600 | Implemented |
SF0335 # 11 Y:2006 | 11 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,262 | $23,694 | Implemented |
SF0335 # 08 Y:2006 | 08 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $32,326 | $37,484 | Implemented |
SF0335 # 05 Y:2006 | 05 | 2006 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $54,378 | $37,915 | Implemented |
SF0335 # 04 Y:2006 | 04 | 2006 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,924 | $4,936 | Implemented |
SF0335 # 03 Y:2006 | 03 | 2006 | INSTALL / REPAIR INSULATION ON STEAM LINES | $3,339 | $1,175 | Implemented |
SF0335 # 09 Y:2006 | 09 | 2006 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $11,683 | $21,175 | Implemented |
SF0335 # 02 Y:2006 | 02 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $60,485 | $21,245 | Implemented |
SF0335 # 01 Y:2006 | 01 | 2006 | REPAIR AND ELIMINATE STEAM LEAKS | $284 | $0 | Implemented |